13514 W RYE ST 91423
Certificate Information: 13514 W RYE ST 91423
- Application / Permit
- 19016-10000-26073
- Plan Check / Job No.
- B19LA17491
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL (N) STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 2/1/2021
- Issuing Office
- Current Status
- CofC Issued on 6/25/2021
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | HANS SANTIAGO |
| Corrections Issued | 10/7/2019 | HANS SANTIAGO |
| Quality Review Completed | 10/9/2019 | SAI KHUM |
| Building Plans Picked Up | 10/10/2019 | APPLICANT |
| Applicant returned to address corrections | 11/19/2019 | HANS SANTIAGO |
| Plan Check Approved | 12/21/2020 | ANDREW SANTIAGO |
| Issued | 2/1/2021 | APPLICANT |
| OK for CofC | 6/1/2021 | KENNETH ROBERTS |
| CofC Issued | 6/25/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2019 | PAMELA TENEZA |
| Housing rent stabilization | Cleared | 1/29/2021 | RICHARD BRINSON |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 6900 CANBY AVE #108 RESEDA, CA 91335 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/3/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Other (see comments) | 4/1/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Other (see comments) | 4/6/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 4/9/2021 | Corrections Issued | JOE VELASQUEZ |
| Structural Steel Frame | 4/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 4/9/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 4/14/2021 | Approved | JOE VELASQUEZ |
| Insulation | 4/14/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 4/14/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 4/14/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 4/19/2021 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 4/20/2021 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 4/28/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 5/4/2021 | Approved | JOE VELASQUEZ |
| Final | 5/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 5/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 5/19/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/19/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 5/19/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 6/1/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 6/1/2021 | Approved | KENNETH ROBERTS |