1142 S SPAULDING AVE 90019
Certificate Information: 1142 S SPAULDING AVE 90019
- Application / Permit
- 19016-10000-26047
- Plan Check / Job No.
- B19LA17471
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LAMC Div. 93. INSTALL NEW FOUR (4) STEEL CANTILEVER COLUMNS.
- Permit Issued
- Issued on 8/31/2020
- Issuing Office
- Current Status
- CofC Issued on 3/16/2021
Permit Application Status History
| Submitted | 8/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2019 | BIDYUT RATH |
| Corrections Issued | 10/10/2019 | BIDYUT RATH |
| Quality Review Completed | 10/16/2019 | SAI KHUM |
| Building Plans Picked Up | 10/25/2019 | APPLICANT |
| Applicant returned to address corrections | 11/21/2019 | BIDYUT RATH |
| Plan Check Approved | 11/21/2019 | BIDYUT RATH |
| Issued | 8/31/2020 | APPLICANT |
| OK for CofC | 3/16/2021 | JONATHAN QUACH |
| CofC Issued | 3/16/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/21/2019 | OSCAR CASTRO |
| Housing rent stabilization | Cleared | 8/17/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2020 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 9/24/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 10/1/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 10/6/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 10/7/2020 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/14/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/14/2020 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 11/19/2020 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 11/20/2020 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/3/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/4/2020 | Approved | DARRYL ARNOLD |
| Final | 12/29/2020 | Not Ready for Inspection | JONATHAN QUACH |
| METHANE-Final | 12/29/2020 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 12/29/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 1/25/2021 | Corrections Issued | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/25/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 1/25/2021 | Approved | JONATHAN QUACH |
| Final | 3/16/2021 | OK for CofC | JONATHAN QUACH |