1611 S BROCKTON AVE 90025
Certificate Information: 1611 S BROCKTON AVE 90025
- Application / Permit
- 19016-10000-25918
- Plan Check / Job No.
- B19LA17391
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL (1) STEEL MOMENT FRAME.
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 9/10/2020
Permit Application Status History
| Submitted | 8/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2019 | DANIEL YIP |
| Corrections Issued | 9/9/2019 | DANIEL YIP |
| Quality Review Completed | 9/9/2019 | SAI KHUM |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Applicant returned to address corrections | 12/5/2019 | DANIEL YIP |
| Applicant returned to address corrections | 1/10/2020 | DANIEL YIP |
| Applicant returned to address corrections | 1/24/2020 | DANIEL YIP |
| Plan Check Approved | 1/27/2020 | DANIEL YIP |
| Issued | 2/27/2020 | LADBS |
| OK for CofC | 8/27/2020 | JOHN DODGE |
| CofC Issued | 9/10/2020 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/24/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Built Development Corporation; Lic. No.: 991996-B | 12400 WILSHIRE BLVD STE 230 LOS ANGELES, CA 90025 |
| Engineer | Hassan,, Mohamed Ali; Lic. No.: S5285 | 3621 HARBOR BLVD #125 SANTA ANA, CA 92704 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/23/2020 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 3/26/2020 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 3/27/2020 | Conditional Approval | JOHN DODGE |
| Deputy Steel/Welding | 4/8/2020 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 4/9/2020 | Approved | JOHN DODGE |
| Structural Steel Frame | 4/16/2020 | Corrections Issued | JOHN DODGE |
| Structural Steel Frame | 4/24/2020 | Partial Approval | JOHN DODGE |
| Wood Frame | 4/27/2020 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 5/6/2020 | Not Ready for Inspection | GRANT WOODS |
| Final | 5/15/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 5/15/2020 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 5/15/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Final | 5/20/2020 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 5/20/2020 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 5/20/2020 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 5/22/2020 | Approved | ALAN NOVAK |
| Final | 6/8/2020 | Not Ready for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/8/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 6/8/2020 | Not Ready for Inspection | GRANT WOODS |
| Final | 6/10/2020 | Corrections Issued | GRANT WOODS |
| Smoke Detectors | 6/10/2020 | Not Ready for Inspection | GRANT WOODS |
| Final | 8/18/2020 | Not Ready for Inspection | JOHN DODGE |
| Smoke Detectors | 8/18/2020 | Not Ready for Inspection | JOHN DODGE |
| Final | 8/24/2020 | Not Ready for Inspection | JOHN DODGE |
| Smoke Detectors | 8/25/2020 | Approved | JOHN DODGE |
| Final | 8/27/2020 | OK for CofC | JOHN DODGE |