2544-2546 S SPAULDING AVE 90016
Certificate Information: 2544-2546 S SPAULDING AVE 90016
- Application / Permit
- 19016-10000-25705
- Plan Check / Job No.
- B19LA17247
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT PER LABC CHAPTER 93. (1) SCCS
- Permit Issued
- Issued on 4/21/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/3/2020
Permit Application Status History
| Submitted | 8/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2019 | THOMAS SHERMAN |
| Corrections Issued | 10/4/2019 | THOMAS SHERMAN |
| Quality Review Completed | 10/4/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 10/11/2019 | APPLICANT |
| Plan Check Approved | 10/30/2019 | THOMAS SHERMAN |
| Issued | 4/21/2020 | LADBS |
| OK for CofC | 8/3/2020 | ERNESTO CORRAL |
| OK to Issue CofC | 8/3/2020 | ERNESTO CORRAL |
| CofC Issued | 8/3/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/12/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2020 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 5/13/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 5/15/2020 | Partial Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/19/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 5/19/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 5/19/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 5/20/2020 | Partial Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 6/18/2020 | Approved | DARRYL ARNOLD |
| Final | 7/2/2020 | Conditional Approval | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2020 | SGSOV Approved | FELIX CEBALLOS |
| Smoke Detectors | 7/2/2020 | Approved | FELIX CEBALLOS |
| Final | 8/3/2020 | OK for CofC | ERNESTO CORRAL |