1215 N BEVERLY VIEW DR 90210
Certificate Information: 1215 N BEVERLY VIEW DR 90210
- Application / Permit
- 19016-10000-25553
- Plan Check / Job No.
- B19LA17118
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of (E) bathroom on first floor. New roofing for (N) HVAC equipment enclosure on roof.
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/24/2023
Permit Application Status History
| Submitted | 8/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | JEFFREY MACHADO |
| Corrections Issued | 9/3/2019 | JEFFREY MACHADO |
| Quality Review Completed | 9/14/2019 | STANLEY RAAP |
| Plan Check Approved | 1/6/2020 | HELEN NGUYEN |
| Issued | 12/6/2021 | APPLICANT |
| Building Plans Picked Up | 12/13/2021 | APPLICANT |
| Permit Finaled | 6/23/2023 | BRENDAN LOONEY |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/25/2019 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 10/25/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2019 | PAMELA TENEZA |
Contact Information
| Contractor | Waconah Construction; Lic. No.: 908219-B | 218 STEPNEY ST INGLEWOOD, CA 90302 |
| Engineer | Ibarra,, Marco Antonio; Lic. No.: C74010 | 16 N MARENGON AVE STE 604 PASADENA, CA 91101 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/2/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/23/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/2/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 6/28/2022 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 6/28/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/1/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 7/1/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 7/7/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/29/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/31/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 8/31/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 9/8/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 9/12/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 9/23/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 6/13/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 6/13/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/16/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 6/16/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 6/16/2023 | Approved | BRENDAN LOONEY |
| Final | 6/23/2023 | Permit Finaled | BRENDAN LOONEY |
| HVAC-Final | 6/23/2023 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 6/23/2023 | Approved | BRENDAN LOONEY |