935 S CAMULOS ST 90023

Certificate Information: 935 S CAMULOS ST 90023

Application / Permit
19016-10000-25539
Plan Check / Job No.
B19LA17108
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 9/23/2020
Issuing Office
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 HELEN NGUYEN
Corrections Issued 8/15/2019 HELEN NGUYEN
Plan Check Approved 9/10/2019 KEVIN MORALES
Issued 9/23/2020 APPLICANT
CofO in Progress 4/5/2021 STUART CHAPMAN
No Progress 4/5/2021 STUART CHAPMAN
No Progress 4/30/2021 RUBEN SALAS
CofO in Progress 4/30/2021 MICHAEL FAUNCE
Permit Expired 5/3/2021 RUBEN SALAS
Permit Finaled 5/8/2021 DEROLD HAUFF
CofO Issued 5/8/2021 DEROLD HAUFF
Permit Finaled 5/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/6/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 9/6/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 9/6/2019 JAMES MORALEZ
Sewer availability Cleared 9/6/2019 JAMES MORALEZ
ZA Case Cleared 9/6/2019 ANNA VAN
ZA Case Cleared 9/6/2019 ANNA VAN
ZI Cleared 9/6/2019 ANNA VAN
Hydrant and Access approval Cleared 9/10/2019 JOHN CONNEALLY

Contact Information

Contractor Altera Construction; Lic. No.: 1036431-B 211 W 92ND STREET      LOS ANGELES, CA 90003

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/14/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 11/14/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 11/24/2020 Approved ROBERT VORHIS
Sewer 11/24/2020 Corrections Issued ROBERT VORHIS
Sewer 12/3/2020 Approved SCOTT FINNILA
ELECTRICAL-Rough 12/10/2020 Approved ROBERT VORHIS
Wood Frame 12/10/2020 Partial Approval ROBERT VORHIS
BUILDING-Rough-Frame 12/15/2020 Approved ROBERT VORHIS
Insulation 12/15/2020 Approved ROBERT VORHIS
MERV13>=Rough 12/15/2020 Approved ROBERT VORHIS
Drywall Nailing 12/18/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 12/18/2020 Approved ROBERT VORHIS
Interior/Exterior Lathing 1/11/2021 Not Ready for Inspection ROBERT VORHIS
Shower Pan 1/11/2021 Not Ready for Inspection ROBERT VORHIS
Interior/Exterior Lathing 1/14/2021 Approved OSVALDO PARAMO
Shower Pan 1/14/2021 Approved OSVALDO PARAMO
ELECTRICAL-Final 2/22/2021 Partial Approval SCOTT FINNILA
Final 2/22/2021 Corrections Issued SCOTT FINNILA
Gas Test 2/22/2021 Approved SCOTT FINNILA
MERV13>=Final 2/22/2021 Approved SCOTT FINNILA
PLUMBING-Final 2/22/2021 Partial Approval SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Approved SCOTT FINNILA
Service/Power Release 2/22/2021 Partial Inspection SCOTT FINNILA
Smoke Detectors 2/22/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 3/3/2021 Approved ROBERT VORHIS
Final 3/3/2021 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Final 3/3/2021 Approved ROBERT VORHIS
Service/Power Release 3/3/2021 Corrections Issued ROBERT VORHIS
ELECTRICAL-Final 3/19/2021 Approved ROBERT VORHIS
Final 3/25/2021 Conditional Approval STUART CHAPMAN
HVAC-Final 3/25/2021 Approved STUART CHAPMAN
Service/Power Release 3/25/2021 Approved STUART CHAPMAN