950 S ST ANDREWS PL 90019
Certificate Information: 950 S ST ANDREWS PL 90019
- Application / Permit
- 19016-10000-25458
- Plan Check / Job No.
- B19LA17056
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 USING PLYWOOD SHEARWALL.
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Metro
- Current Status
- CofC Issued on 5/24/2021
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2019 | VARAND SARKISIAN |
| Corrections Issued | 9/23/2019 | VARAND SARKISIAN |
| Quality Review Completed | 9/25/2019 | SAI KHUM |
| Building Plans Picked Up | 9/26/2019 | APPLICANT |
| Plan Check Approved | 11/14/2019 | VARAND SARKISIAN |
| Issued | 1/4/2021 | APPLICANT |
| OK for CofC | 5/14/2021 | DARRYL ARNOLD |
| CofC Issued | 5/24/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/4/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-A | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/10/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/18/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 4/1/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 4/1/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/1/2021 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 4/13/2021 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 4/13/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/20/2021 | Approved | MARK FERRARI |
| Final | 5/13/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/13/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/13/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 5/14/2021 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/14/2021 | Approved | DARRYL ARNOLD |