1820 S 4TH AVE 90019
Certificate Information: 1820 S 4TH AVE 90019
- Application / Permit
- 19016-10000-25368
- Plan Check / Job No.
- B19LA16973
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- TENANT IMPROVEMENT OF (E) 2-STORY BUILDING: CONVERT (E) RETAIL TO OFFICE, CONVERT (E) DAYCARE TO 2 BEDROOM MANAGER UNIT AND OFFICE. SECOND FLOOR UNITS TO REMAIN, (E) FINISHES & CABINETRY TO BE REPLACED. (E) ROOING MATERIAL AND (E) SECOND FLOOR WINDOWS TO BE REPLACED-SAME SIZE SAME LOCATIONS (E) LANDSCAPE & HARDSCAPE TO BE REPLACED. NO IMPACT TOOLS TO BE USED. RESTRIPE PARKING
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- CofO Issued on 7/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2019 | VU NGUYEN |
| Corrections Issued | 9/9/2019 | JEFFREY MACHADO |
| Disabled Access Plans Picked Up | 9/9/2019 | APPLICANT |
| Green Plans Picked Up | 9/16/2019 | APPLICANT |
| Quality Review Completed | 9/21/2019 | STANLEY RAAP |
| Building Plans Picked Up | 9/27/2019 | APPLICANT |
| Plan Check Approved | 12/10/2019 | VU NGUYEN |
| Issued | 12/8/2020 | APPLICANT |
| CofO in Progress | 7/20/2022 | TIMOTHY BUXTON |
| CofO Issued | 7/26/2022 | TED RIES |
| Permit Finaled | 7/26/2022 | TED RIES |
Permit Application Clearance Information
| Green Code | Cleared | 9/9/2019 | SARAH ABOULHOSN |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/8/2019 | THOMAS LANG |
| Fire Marshall Fire Life Safety | Cleared | 11/22/2019 | DOMINIQUE MEDINA |
| Project located in CRA area | Cleared | 11/25/2019 | GISELLE CORELLA |
| Public Housing | Cleared | 12/2/2019 | STANLEY YU |
| DAS Clearance | Cleared | 12/6/2019 | SHINE LIN |
| Community Plan Implem. Overlay | Cleared | 3/18/2020 | KYLE WINSTON |
| Housing rent stabilization | Cleared | 12/2/2020 | PHILLIP MUNGUIA |
Contact Information
| Architect | Barar,, Ali; Lic. No.: C25584 | 624 SOUTH ORANGE GROVE BLVD. PASADENA, CA 91105 |
| Contractor | Westport Construction Inc; Lic. No.: 712732-B | 125 W MAPLE AVE MONROVIA, CA 91016 |
| Engineer | Yeh,, Ming-Yang; Lic. No.: S2587 | 131 WEST GREEN ST PASADENA, CA 911059886 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 4/6/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 4/9/2021 | Partial Approval | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | TIMOTHY BUXTON |
| Final | 4/28/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 4/28/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Rough | 4/28/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Final | 4/28/2021 | Approved | TIMOTHY BUXTON |
| METHANE-Rough | 4/28/2021 | Approved | TIMOTHY BUXTON |
| Reinforced Masonry Frame | 4/28/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 4/28/2021 | Approved | TIMOTHY BUXTON |
| Special/Order Compliance | 4/29/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 5/11/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 5/12/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Wood Frame | 5/12/2021 | Approved | TIMOTHY BUXTON |
| Deputy Steel/Welding | 5/13/2021 | Conditional Approval | TIMOTHY BUXTON |
| Wood Frame | 5/24/2021 | Not Ready for Inspection | DAVID BURKHEAD |
| Wood Frame | 5/25/2021 | Partial Approval | TIMOTHY BUXTON |
| Final | 6/2/2021 | Partial Approval | TIMOTHY BUXTON |
| Green Building Final | 6/2/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 6/17/2021 | Partial Approval | TIMOTHY BUXTON |
| Insulation | 6/24/2021 | Partial Approval | TIMOTHY BUXTON |
| Wood Frame | 6/24/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 7/22/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 7/30/2021 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 8/9/2021 | Partial Approval | EDWIN GREGORYONA |
| Final | 9/27/2021 | Partial Approval | TIMOTHY BUXTON |
| Final | 10/5/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 10/22/2021 | Conditional Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 10/22/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 10/29/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 11/1/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 11/1/2021 | Conditional Approval | TIMOTHY BUXTON |
| Drywall Nailing | 11/12/2021 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 11/12/2021 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 11/17/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 11/29/2021 | Approved | TIMOTHY BUXTON |
| T-Bar Ceiling | 1/4/2022 | Approved | TIMOTHY BUXTON |
| Excavation/Setback/Form/Re-Bar | 1/11/2022 | Approved | TIMOTHY BUXTON |
| Masonry Wall/Backfill | 1/11/2022 | Approved | TIMOTHY BUXTON |
| Final | 6/15/2022 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 6/21/2022 | Not Ready for Inspection | TIMOTHY BUXTON |