6022 W ROMAINE ST 90038

Certificate Information: 6022 W ROMAINE ST 90038

Application / Permit
19016-10000-25119
Plan Check / Job No.
B19LA16814
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LAMC CH 93. INSTALL (4) SCCS
Permit Issued
Issued on 3/16/2020
Issuing Office
Metro
Current Status
CofC Issued on 6/18/2020

Permit Application Status History

Submitted 8/12/2019 APPLICANT
Assigned to Plan Check Engineer 9/18/2019 DANIEL SANJUAN
Corrections Issued 9/25/2019 DANIEL SANJUAN
Quality Review Completed 10/2/2019 SAI KHUM
Building Plans Picked Up 10/11/2019 APPLICANT
Plan Check Approved 10/23/2019 DANIEL SANJUAN
Issued 3/16/2020 LADBS
OK for CofC 6/17/2020 FELIX CEBALLOS
CofC Issued 6/18/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 2/24/2020 MICHAEL GREGERSON

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2020 Corrections Issued BRUCE CAMPBELL
Wood Frame 4/7/2020 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 4/21/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 4/21/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 4/22/2020 Approved FELIX CEBALLOS
Footing/Foundation/Slab 4/22/2020 Approved FELIX CEBALLOS
Deputy Steel/Welding 5/29/2020 Partial Approval FELIX CEBALLOS
Structural Steel Frame 5/29/2020 Partial Approval MARK FERRARI
Wood Frame 5/29/2020 Corrections Issued MARK FERRARI
Deputy Steel/Welding 6/5/2020 Partial Approval FELIX CEBALLOS
Structural Steel Frame 6/5/2020 Approved FELIX CEBALLOS
Wood Frame 6/5/2020 Approved FELIX CEBALLOS
Interior/Exterior Lathing 6/10/2020 Approved FELIX CEBALLOS
Final 6/17/2020 OK for CofC FELIX CEBALLOS
SGSOV-Seismic Gas S/O Valve 6/17/2020 SGSOV Approved FELIX CEBALLOS
Smoke Detectors 6/17/2020 Approved FELIX CEBALLOS