2813 S 5TH AVE 90018
Certificate Information: 2813 S 5TH AVE 90018
- Application / Permit
- 19016-10000-25007
- Plan Check / Job No.
- B19LA16761
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1'-6" X 23'-6" ADDITION TO THE FRONT OF (E) GARAGE AND RENOVATION OF EXISITNG SINGLE FAMILY DWELLING INCLUDING REMODELING OF BATHROOMS AND BEDROOMS, MODIFICATION OF INTERIOR PARTITION WALLS "COMPLY WITH DEPARTMENT ORDER effective date 10/10/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/27/2019 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 9/9/2019 | YOUNG KIM |
| Green Plans Picked Up | 9/9/2019 | APPLICANT |
| Plan Check Approved | 12/4/2019 | FARSHAD ALIMOHAMADI |
| Issued | 10/14/2021 | APPLICANT |
| CofO in Progress | 1/6/2022 | SCOTT FINNILA |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| Permit Finaled | 3/5/2022 | DEROLD HAUFF |
| CofO Issued | 3/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2019 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 10/4/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 11/4/2019 | VIVIAN LAO |
| HPOZ | Cleared | 11/15/2019 | LYDIA CHAPMAN |
Contact Information
| Architect | Ziese,, Daniel J; Lic. No.: C32234 | 612 MOULTON AVENUE UNIT 7 LOS ANGELES, CA 90031 |
| Contractor | Doobek Builders; Lic. No.: 980653-B | 5308 DERRY AVE I-101, 102 AGOURA HILLS, CA 91301 |
| Engineer | Volpe,, Robert Matthew; Lic. No.: C25116 | 20321 LAKE FOREST DRIVE STE D6 LAKE FOREST, CA 92630 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2021 | Approved | STUART CHAPMAN |
| Insulation | 11/23/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/23/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 11/23/2021 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 12/2/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 12/2/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/2/2021 | Partial Approval | STUART CHAPMAN |
| Final | 12/29/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 12/29/2021 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 12/29/2021 | SGSOV Not Ready | SCOTT FINNILA |
| Smoke Detectors | 12/29/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 1/6/2022 | Approved | SCOTT FINNILA |
| Final | 1/6/2022 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 1/6/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 1/6/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 1/6/2022 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 1/6/2022 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 1/6/2022 | Approved | SCOTT FINNILA |