407 S MOLINO ST 90013

Certificate Information: 407 S MOLINO ST 90013

Application / Permit
19016-10000-24862
Plan Check / Job No.
B19LA16682
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Change of use from Public Garage/Auto Repair to Creative Office. Tenant Improvement to (E) industrial building. New storefront system in (E) openings, re-roof over existing sheathing, new skylights, new ADA restrooms. (URM Building)
Permit Issued
Issued on 2/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2019 APPLICANT
Assigned to Plan Check Engineer 8/22/2019 SALVADOR QUINTANILLA
Disabled Access Plans Picked Up 8/26/2019 APPLICANT
Green Plans Picked Up 8/26/2019 APPLICANT
Corrections Issued 9/10/2019 SALVADOR QUINTANILLA
Quality Review Completed 9/16/2019 GARO TELMI
Building Plans Picked Up 9/17/2019 APPLICANT
Applicant returned to address corrections 10/29/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 11/12/2019 SALVADOR QUINTANILLA
Applicant returned to address corrections 12/26/2019 SALVADOR QUINTANILLA
Plan Check Approved 1/8/2020 SALVADOR QUINTANILLA
Issued 2/18/2020 LADBS
CofO in Progress 5/5/2022 KATY RAMIREZ
CofO Issued 5/5/2022 ERNESTO CORRAL
Permit Finaled 5/5/2022 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/12/2019 ERIK BEASLEY
Project located in CRA area Cleared 9/13/2019 JIM URQUHART
ZA Case Cleared 9/17/2019 TREVOR MARTIN
ZI Cleared 9/17/2019 TREVOR MARTIN
DAS Clearance Cleared 10/28/2019 SHINE LIN
Green Code Cleared 11/4/2019 SALVADOR QUINTANILLA
Sewer availability Cleared 11/4/2019 JAMES KHO

Contact Information

Contractor California Electric & Construction Services Inc; Lic. No.: 680634-B 1301 S MAIN STREET      LOS ANGELES, CA 90015

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/4/2020 Not Ready for Inspection LANNY MERRICK
Pre-Inspection 4/6/2021 Partial Inspection KATY RAMIREZ
Special/Order Compliance 6/11/2021 Approved DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 8/18/2021 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 8/19/2021 Not Ready for Inspection JONATHAN QUACH
Wood Frame 8/19/2021 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 9/1/2021 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 9/7/2021 Partial Inspection KATY RAMIREZ
Green Building Final 4/8/2022 Not Ready for Inspection KATY RAMIREZ
METHANE-Final 4/8/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 4/8/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 4/14/2022 Partial Inspection KATY RAMIREZ
Final 4/21/2022 Partial Inspection KATY RAMIREZ
Green Building Final 4/21/2022 Approved KATY RAMIREZ
METHANE-Final 4/21/2022 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 4/21/2022 Approved KATY RAMIREZ
Final 5/4/2022 Partial Inspection KATY RAMIREZ
Final 5/5/2022 OK to Issue CofO KATY RAMIREZ