4810 W ST ELMO DR 90019
Certificate Information: 4810 W ST ELMO DR 90019
- Application / Permit
- 19016-10000-24751
- Plan Check / Job No.
- B19LA16578
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93, 4 (N) SCCS AND WOOD SHEAR WALL.
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/5/2021
Permit Application Status History
| Submitted | 8/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2019 | VARAND SARKISIAN |
| Corrections Issued | 9/4/2019 | VARAND SARKISIAN |
| Quality Review Completed | 9/5/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Plan Check Approved | 12/20/2019 | VARAND SARKISIAN |
| Issued | 2/4/2020 | LADBS |
| OK for CofC | 3/2/2021 | MARK FERRARI |
| CofC Issued | 3/5/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/31/2020 | CHARLES GARCIA |
Contact Information
| Contractor | W S Construction Co; Lic. No.: 521254-B | 12219 CREEKWOOD AVE CERRITOS, CA 90703 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 10/9/2020 | Partial Approval | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 11/13/2020 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 11/13/2020 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 12/4/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 12/10/2020 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/15/2020 | Approved | DARRYL ARNOLD |
| Final | 1/26/2021 | Conditional Approval | JONATHAN QUACH |
| METHANE-Final | 1/26/2021 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 1/26/2021 | Approved | JONATHAN QUACH |
| Final | 3/2/2021 | OK for CofC | MARK FERRARI |