910 N ALFRED ST 90069
Certificate Information: 910 N ALFRED ST 90069
- Application / Permit
- 19016-10000-24552
- Plan Check / Job No.
- B19LA16433
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 822 :: Soft-Story seismic retrofit per LABC Chapter 93: Install 2 new SCCS and grade beam.
- Permit Issued
- Issued on 7/29/2020
- Issuing Office
- Current Status
- CofC Issued on 11/10/2020
Permit Application Status History
| Submitted | 8/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2019 | VARAND SARKISIAN |
| Corrections Issued | 9/13/2019 | VARAND SARKISIAN |
| Re-Submittal Required | 9/19/2019 | HANS SANTIAGO |
| Re-Submitted | 3/23/2020 | VARAND SARKISIAN |
| Corrections Issued 2 | 3/23/2020 | VARAND SARKISIAN |
| Submitted for Second Quality Review | 3/23/2020 | VARAND SARKISIAN |
| Quality Review Completed | 3/23/2020 | SAI KHUM |
| Plan Check Approved | 3/23/2020 | VARAND SARKISIAN |
| Issued | 7/29/2020 | APPLICANT |
| OK for CofC | 10/23/2020 | JONATHAN QUACH |
| CofC Issued | 11/10/2020 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/31/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 6900 CANBY AVE #108 RESEDA, CA 91335 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/7/2020 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Drilled-In Anchors | 8/19/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 8/19/2020 | Conditional Approval | MARK FERRARI |
| Deputy Other (see comments) | 8/24/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 8/24/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/26/2020 | Approved | VAHE KELEDJIAN |
| Structural Steel Frame | 8/26/2020 | Approved | VAHE KELEDJIAN |
| Wood Frame | 8/26/2020 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Reinf. Concrete | 9/4/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 9/14/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 9/17/2020 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 9/25/2020 | Conditional Approval | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 10/9/2020 | Approved | JONATHAN QUACH |
| Final | 10/23/2020 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 10/23/2020 | Approved | JONATHAN QUACH |