1400 N SUTHERLAND ST 90026

Certificate Information: 1400 N SUTHERLAND ST 90026

Application / Permit
19016-10000-24497
Plan Check / Job No.
B19LA16391
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan 819 :: Soft-Story seismic retrofit per LABC Chapter 93: USING (1) ORDINARY MOMENT FRAME WITH GRADE BEAM.
Permit Issued
Issued on 7/14/2020
Issuing Office
Current Status
CofC Issued on 5/19/2022

Permit Application Status History

Submitted 8/7/2019 APPLICANT
Assigned to Plan Check Engineer 9/4/2019 DANIEL YIP
Corrections Issued 9/11/2019 DANIEL YIP
Quality Review Completed 9/16/2019 HANS SANTIAGO
Applicant returned to address corrections 11/6/2019 DANIEL YIP
Applicant returned to address corrections 3/2/2020 DANIEL YIP
Plan Check Approved 4/23/2020 DANIEL YIP
Issued 7/14/2020 APPLICANT
OK for CofC 5/19/2022 MARK FERRARI
CofC Issued 5/19/2022 WINSTON DUNNING

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/19/2020 JEANIE LAM
Work Adjacent to Public Way Cleared 4/16/2020 ARMEN SARKISIAN
Housing rent stabilization Cleared 7/7/2020 MICHAEL SOTO

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2020 Corrections Issued MARK FERRARI
Pre-Inspection 10/20/2020 Approved MARK FERRARI
Deputy Drilled-In Anchors 10/30/2020 Approved MARK FERRARI
Footing/Foundation/Slab 10/30/2020 Approved MARK FERRARI
Structural Steel Frame 10/30/2020 Approved MARK FERRARI
Wood Frame 10/30/2020 Approved MARK FERRARI
Drywall Nailing 11/4/2020 Approved MARK FERRARI
Interior/Exterior Lathing 11/4/2020 Corrections Issued MARK FERRARI
Interior/Exterior Lathing 11/6/2020 Approved MARK FERRARI
Final 11/18/2020 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Not Ready MARK FERRARI
Smoke Detectors 11/18/2020 Not Ready for Inspection MARK FERRARI
Final 5/19/2022 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved MARK FERRARI
Smoke Detectors 5/19/2022 Approved MARK FERRARI