14201 W DELANO ST 91401
Certificate Information: 14201 W DELANO ST 91401
- Application / Permit
- 19016-10000-24493
- Plan Check / Job No.
- B19LA16387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 817 :: Soft-Story seismic retrofit per LABC Chapter 93: USING (1) STEEL SPECIAL CANTILEVERED COLUMN AND GRADE BEAM.
- Permit Issued
- Issued on 12/16/2020
- Issuing Office
- Current Status
- CofC Issued on 3/3/2021
Permit Application Status History
| Submitted | 8/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2019 | JESSE VIDUYA |
| Corrections Issued | 9/10/2019 | THOMAS SHERMAN |
| Quality Review Completed | 9/12/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/4/2020 | THOMAS SHERMAN |
| Plan Check Approved | 11/9/2020 | JESSE VIDUYA |
| Issued | 12/16/2020 | APPLICANT |
| OK for CofC | 2/26/2021 | KENNETH ROBERTS |
| CofC Issued | 3/3/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/14/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | S F T Construction Corp; Lic. No.: 1009086-B | 322 6TH STREET UNIT 4 SAN FRANCISCO, CA 94103 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/7/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Wood Construction | 1/14/2021 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 1/14/2021 | Partial Approval | JOE VELASQUEZ |
| Insulation | 1/15/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 1/20/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 1/20/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 1/20/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 1/22/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 1/27/2021 | Approved | JOE VELASQUEZ |
| Final | 2/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 2/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 2/26/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 2/26/2021 | Approved | KENNETH ROBERTS |