11205 S BROADWAY 90061

Certificate Information: 11205 S BROADWAY 90061

Application / Permit
19016-10000-24482
Plan Check / Job No.
B19LA16373
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: USING (1) SPECIAL CANTILEVERED COLUMN AND GRADE BEAM.
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofC Issued on 2/20/2024

Permit Application Status History

Submitted 8/7/2019 APPLICANT
Assigned to Plan Check Engineer 9/4/2019 DANIEL SANJUAN
Corrections Issued 9/12/2019 DANIEL SANJUAN
Quality Review Completed 9/19/2019 HANS SANTIAGO
Plan Check Approved 12/23/2019 DANIEL SANJUAN
Issued 3/2/2022 APPLICANT
OK for CofC 8/8/2023 DARRYL ARNOLD
CofC Issued 2/20/2024 WINSTON DUNNING

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 9/20/2019 JAMES MORALEZ
Project located in CRA area Cleared 10/1/2019 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 10/3/2019 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 11/13/2019 HELEN JADALI
Housing rent stabilization Cleared 9/20/2021 RICARDO BOHORQUEZ

Contact Information

Contractor Vickers Construction Company Inc; Lic. No.: 1008338-B 952 E 116TH STREET      LOS ANGELES, CA 90059
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/8/2022 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 5/10/2022 Corrections Issued DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 6/6/2022 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 6/6/2022 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 6/9/2022 Corrections Issued DARRYL ARNOLD
Interior/Exterior Lathing 6/9/2022 Conditional Approval DARRYL ARNOLD
Final 7/1/2022 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 7/1/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 7/1/2022 Not Ready for Inspection DARRYL ARNOLD
Final 10/14/2022 Corrections Issued DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 10/14/2022 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 10/14/2022 Approved DARRYL ARNOLD
Final 12/1/2022 Conditional Approval DARRYL ARNOLD
Final 8/8/2023 OK for CofC DARRYL ARNOLD