3274-3276 E FOLSOM ST 90063
Certificate Information: 3274-3276 E FOLSOM ST 90063
- Application / Permit
- 19016-10000-24441
- Plan Check / Job No.
- B19LA16340
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT (E) ATTACHED GARAGE/STORAGE (36'-0" X 22'-0") AT 1ST FLOOR OF AN EXITING TWO STORY DUPLEX TO ACCESSORY DWELLING UNIT PER STATE GENREAL CODE SECTION 65852.2(e)(1)(C).
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 11/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2019 | APPLICANT |
| Green Plans Picked Up | 8/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | TSE MING HUANG |
| Corrections Issued | 9/16/2019 | TSE MING HUANG |
| Quality Review Completed | 9/21/2019 | STANLEY RAAP |
| Plan Check Approved | 8/18/2020 | STANLEY RAAP |
| Issued | 8/26/2020 | APPLICANT |
| Building Plans Picked Up | 9/1/2020 | APPLICANT |
| CofO in Progress | 11/4/2021 | RUBEN SALAS |
| CofO in Progress | 11/4/2021 | RUBEN SALAS |
| Permit Finaled | 11/5/2021 | DEROLD HAUFF |
| Permit Finaled | 11/5/2021 | DEROLD HAUFF |
| CofO Issued | 11/5/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 9/5/2019 | SARAH ABOULHOSN |
| Address approval | Cleared | 7/16/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2020 | ELAINE LEI |
| Sewer availability | Cleared | 7/16/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALIZAH MAYAGOITIA, (213) 202-3124 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2020 | Corrections Issued | RUBEN SALAS |
| Insulation | 2/16/2021 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 2/26/2021 | Corrections Issued | RUBEN SALAS |
| Green Building Rough | 2/26/2021 | Not Ready for Inspection | RUBEN SALAS |
| Insulation | 2/26/2021 | Not Ready for Inspection | RUBEN SALAS |
| Drywall Nailing | 4/23/2021 | Corrections Issued | RUBEN SALAS |
| BUILDING-Rough-Frame | 6/10/2021 | Approved | RUBEN SALAS |
| Drywall Nailing | 6/10/2021 | Approved | RUBEN SALAS |
| Green Building Final | 6/10/2021 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Rough | 6/10/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Not Ready | RUBEN SALAS |
| Smoke Detectors | 6/10/2021 | Not Ready for Inspection | RUBEN SALAS |
| Final | 10/13/2021 | Corrections Issued | RUBEN SALAS |
| Green Building Final | 10/13/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Not Ready | RUBEN SALAS |
| Smoke Detectors | 10/13/2021 | Approved | RUBEN SALAS |
| Final | 11/1/2021 | Corrections Issued | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Approved | RUBEN SALAS |
| Final | 11/4/2021 | OK to Issue CofO | RUBEN SALAS |