1052 S BRONSON AVE 90019
Certificate Information: 1052 S BRONSON AVE 90019
- Application / Permit
- 19016-10000-24176
- Plan Check / Job No.
- B19LA16151
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND STORAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB 229.
- Permit Issued
- Issued on 12/11/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | CRISTINA SALAZAR |
| Corrections Issued | 9/3/2019 | CRISTINA SALAZAR |
| Quality Review Completed | 9/7/2019 | STANLEY RAAP |
| Building Plans Picked Up | 9/13/2019 | APPLICANT |
| Green Plans Picked Up | 9/13/2019 | APPLICANT |
| Applicant returned to address corrections | 9/25/2019 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 10/8/2019 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/6/2019 | CRISTINA SALAZAR |
| Plan Check Approved | 12/6/2019 | CRISTINA SALAZAR |
| Plan Check Approved | 12/9/2019 | CRISTINA SALAZAR |
| Issued | 12/11/2019 | LADBS |
| CofO in Progress | 9/22/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
| CofO Issued | 9/25/2021 | DEROLD HAUFF |
| Permit Finaled | 9/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/25/2019 | ERIK BEASLEY |
| Green Code | Cleared | 9/26/2019 | SARAH ABOULHOSN |
| CPC | Cleared | 10/3/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 10/3/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 10/3/2019 | JEANETTE VONG |
| City Hist. Cultural Monument | Cleared | 12/2/2019 | BRADLEY FURUYA |
| HPOZ | Cleared | 12/2/2019 | BRADLEY FURUYA |
| Historic monument | Cleared | 12/2/2019 | BRADLEY FURUYA |
Contact Information
| Architect | , ; Lic. No.: C37928 | 3470 WILSHIRE BLVD. LOS ANGELES, CA 90010 |
| Contractor | Jella Construction Inc; Lic. No.: 1012736-B | 10207 MOUNTAIR AVENUE #107 TUJUNGA, CA 91042 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/17/2020 | Approved | LUIS BARRALES |
| Excavation/Setback/Form/Re-Bar | 2/21/2020 | Corrections Issued | BRAD BESCOS |
| Pre-Inspection | 2/21/2020 | Approved | BRAD BESCOS |
| Footing/Foundation/Slab | 4/17/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 5/22/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Insulation | 5/27/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/5/2020 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Rough | 6/5/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/5/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pre-Inspection | 6/9/2020 | Partial Approval | ARTHUR SARGSYAN |
| Drywall Nailing | 6/11/2020 | No Access for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 6/11/2020 | No Access for Inspection | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 6/11/2020 | No Access for Inspection | ARTHUR SARGSYAN |
| Pre-Inspection | 6/11/2020 | No Access for Inspection | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 6/15/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Drywall Nailing | 6/17/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 6/17/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 7/6/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| FLOOD-Proofing Certificate | 7/6/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Final | 7/6/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/6/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| METHANE-Final | 7/6/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 7/6/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2021 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/6/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| FLOOD-Proofing Certificate | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 7/12/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/12/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 7/20/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Final | 8/25/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 9/21/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |