203 W OPP ST 90744
Certificate Information: 203 W OPP ST 90744
- Application / Permit
- 19016-10000-24115
- Plan Check / Job No.
- B19LA16118
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 4 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
- Permit Issued
- Issued on 9/24/2020
- Issuing Office
- Current Status
- CofC Issued on 3/1/2021
Permit Application Status History
| Submitted | 8/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2019 | ERWIN PASCUA |
| Corrections Issued | 9/10/2019 | ERWIN PASCUA |
| Quality Review Completed | 9/11/2019 | SAI KHUM |
| Building Plans Picked Up | 9/13/2019 | APPLICANT |
| Applicant returned to address corrections | 10/11/2019 | ERWIN PASCUA |
| Plan Check Approved | 10/30/2019 | ERWIN PASCUA |
| Issued | 9/24/2020 | APPLICANT |
| OK for CofC | 2/26/2021 | JOEY BUCHANAN |
| CofC Issued | 3/1/2021 | NICK LAROCCA |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/11/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Brytin Construction; Lic. No.: 1065160-B | 1140 AGNEW STREET SIMI VALLEY, CA 93065 |
| Engineer | Pachunuri,, Nalin Kumar; Lic. No.: C78970 | 21126 INGOMAR CT CANOGA PARK, CA 91304 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/1/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 10/6/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 10/8/2020 | Partial Approval | JOEY BUCHANAN |
| Footing/Foundation/Slab | 10/13/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/14/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 10/20/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 10/21/2020 | Approved | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 11/4/2020 | Approved | JOEY BUCHANAN |
| Final | 2/26/2021 | OK for CofC | JOEY BUCHANAN |
| METHANE-Final | 2/26/2021 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 2/26/2021 | Approved | JOEY BUCHANAN |