4553 W 17TH ST 90019
Certificate Information: 4553 W 17TH ST 90019
- Application / Permit
- 19016-10000-23688
- Plan Check / Job No.
- B19LA15817
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 2 SCCS.
- Permit Issued
- Issued on 12/7/2020
- Issuing Office
- Current Status
- CofC Issued on 5/11/2021
Permit Application Status History
| Submitted | 7/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2019 | DANIEL YIP |
| Corrections Issued | 9/9/2019 | DANIEL YIP |
| Quality Review Completed | 9/9/2019 | SAI KHUM |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Plan Check Approved | 9/12/2019 | DANIEL YIP |
| Issued | 12/7/2020 | APPLICANT |
| OK for CofC | 4/26/2021 | MARK FERRARI |
| OK to Issue CofC | 4/26/2021 | ERNESTO CORRAL |
| CofC Issued | 5/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 11/16/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/14/2021 | Corrections Issued | JONATHAN QUACH |
| Footing/Foundation/Slab | 2/5/2021 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 2/8/2021 | Partial Inspection | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 2/9/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 3/5/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/19/2021 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 3/19/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 3/19/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/5/2021 | Approved | DARRYL ARNOLD |
| Final | 4/15/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 4/15/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/15/2021 | SGSOV No Gas | DARRYL ARNOLD |
| Smoke Detectors | 4/15/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 4/22/2021 | Conditional Approval | MARK FERRARI |
| METHANE-Final | 4/22/2021 | Approved | MARK FERRARI |
| Smoke Detectors | 4/22/2021 | Approved | MARK FERRARI |
| Final | 4/26/2021 | OK for CofC | MARK FERRARI |