11336 W LANDALE ST 91602
Certificate Information: 11336 W LANDALE ST 91602
- Application / Permit
- 19016-10000-23587
- Plan Check / Job No.
- B19LA15774
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH 93. (1) SCCS.
- Permit Issued
- Issued on 7/17/2020
- Issuing Office
- Current Status
- CofC Issued on 1/4/2021
Permit Application Status History
| Submitted | 7/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2019 | DANIEL YIP |
| Corrections Issued | 9/9/2019 | DANIEL YIP |
| Quality Review Completed | 9/9/2019 | SAI KHUM |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Plan Check Approved | 7/17/2020 | DANIEL YIP |
| Issued | 7/17/2020 | APPLICANT |
| OK for CofC | 12/14/2020 | JOE VELASQUEZ |
| CofC Issued | 1/4/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/17/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Cedar Construction & Development Inc; Lic. No.: 554550-B | 10234 NATIONAL BLVD #1 LOS ANGELES, CA 90034 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/31/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Pre-Inspection | 8/3/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 8/14/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 8/19/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 9/14/2020 | No Access for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 9/14/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/17/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/18/2020 | No Access for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 9/18/2020 | Approved | JOE VELASQUEZ |
| Footing/Foundation/Slab | 9/18/2020 | Approved | JOE VELASQUEZ |
| Piling/Pier/Caisson | 9/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 9/22/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 9/23/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 9/23/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 10/2/2020 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 11/10/2020 | Approved | JOE VELASQUEZ |
| Final | 12/14/2020 | OK for CofC | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/14/2020 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 12/14/2020 | Approved | JOE VELASQUEZ |