5821 W VIRGINIA AVE 90038
Certificate Information: 5821 W VIRGINIA AVE 90038
- Application / Permit
- 19016-10000-23034
- Plan Check / Job No.
- B19LA15425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH 93. (2) SCCS.
- Permit Issued
- Issued on 12/14/2020
- Issuing Office
- Current Status
- CofC Issued on 3/1/2021
Permit Application Status History
| Submitted | 7/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2019 | ERICK RIVERA |
| Corrections Issued | 9/4/2019 | ERICK RIVERA |
| Quality Review Completed | 9/5/2019 | SAI KHUM |
| Building Plans Picked Up | 9/6/2019 | APPLICANT |
| Applicant returned to address corrections | 10/30/2019 | ERICK RIVERA |
| Plan Check Approved | 11/12/2019 | ERICK RIVERA |
| Issued | 12/14/2020 | APPLICANT |
| OK for CofC | 2/23/2021 | JONATHAN QUACH |
| CofC Issued | 3/1/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 10/31/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 12/14/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2021 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 1/7/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Steel/Welding | 1/7/2021 | Approved | JONATHAN QUACH |
| Footing/Foundation/Slab | 1/7/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 1/7/2021 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 1/7/2021 | Partial Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 1/11/2021 | Conditional Approval | JONATHAN QUACH |
| Wood Frame | 1/11/2021 | Partial Approval | JONATHAN QUACH |
| Wood Frame | 1/12/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 1/15/2021 | Corrections Issued | JONATHAN QUACH |
| Final | 2/23/2021 | OK for CofC | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 2/23/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 2/23/2021 | Approved | JONATHAN QUACH |