3200 S BAGLEY AVE 90034
Certificate Information: 3200 S BAGLEY AVE 90034
- Application / Permit
- 19016-10000-22970
- Plan Check / Job No.
- B19LA15377
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 2 (N) SCCS AND SHEAR WALLS
- Permit Issued
- Issued on 11/4/2021
- Issuing Office
- Current Status
- Issued on 11/4/2021
Permit Application Status History
| Submitted | 7/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2019 | DANIEL SANJUAN |
| Corrections Issued | 9/4/2019 | DANIEL SANJUAN |
| Quality Review Completed | 9/5/2019 | SAI KHUM |
| Applicant returned to address corrections | 8/16/2021 | DANIEL SANJUAN |
| Plan Check Approved | 9/9/2021 | DANIEL SANJUAN |
| Issued | 11/4/2021 | APPLICANT |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/13/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Basseri Engineering & Construction; Lic. No.: 724559-B | 5250 W CENTRY BLVD #300 LOS ANGELES, CA 90045 |
| Engineer | Basseri,, Siavash; Lic. No.: C45487 | 5250 W CENTURY BLVD STE 300 LOS ANGELES, CA 90045 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/6/2021 | Approved | PAUL DAVIDSON |
| Wood Frame | 12/6/2021 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 1/20/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 1/20/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| Footing/Foundation/Slab | 4/21/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 4/21/2022 | Partial Approval | PAUL DAVIDSON |
| Wood Frame | 6/9/2022 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 6/10/2022 | Partial Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 6/22/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 7/8/2022 | Approved | NICK LAROCCA |
| Interior/Exterior Lathing | 7/15/2022 | Approved | GRANT WOODS |
| Final | 8/8/2022 | Not Ready for Inspection | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Not Ready | NICK LAROCCA |
| Smoke Detectors | 8/8/2022 | Not Ready for Inspection | NICK LAROCCA |