3152 W SAN MARINO ST 90006

Certificate Information: 3152 W SAN MARINO ST 90006

Application / Permit
19016-10000-22927
Plan Check / Job No.
B19LA15352
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 3 (HFX) HARDY FRAME SHEAR WALL SYSTEM.
Permit Issued
Issued on 3/12/2020
Issuing Office
Metro
Current Status
CofC Issued on 3/19/2024

Permit Application Status History

Submitted 7/25/2019 APPLICANT
Assigned to Plan Check Engineer 8/28/2019 DANIEL SANJUAN
Corrections Issued 9/4/2019 DANIEL SANJUAN
Quality Review Completed 9/5/2019 SAI KHUM
Building Plans Picked Up 9/6/2019 APPLICANT
Plan Check Approved 1/29/2020 DANIEL SANJUAN
Issued 3/12/2020 LADBS
OK for CofC 5/12/2020 DARRYL ARNOLD
CofC Issued 3/19/2024 WINSTON DUNNING

Permit Application Clearance Information

Project located in CRA area Cleared 1/14/2020 LAMBERT GIESSINGER
Housing rent stabilization Cleared 2/12/2020 MICHAEL GREGERSON

Contact Information

Contractor Sks Construction; Lic. No.: 720390-B 5104 GARDEN GROVE AVE      TARZANA, CA 91356
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 5104 GARDEN GROVE      TARZANA, CA 91356

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/27/2020 Approved MARK FERRARI
Deputy Drilled-In Anchors 4/14/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 4/17/2020 Approved MARK FERRARI
Wood Frame 4/17/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 4/20/2020 Partial Approval FELIX CEBALLOS
Deputy Reinf. Concrete 4/22/2020 Partial Approval DARRYL ARNOLD
Deputy Reinf. Concrete 4/23/2020 Partial Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Approved DARRYL ARNOLD
Wood Frame 4/24/2020 Approved DARRYL ARNOLD
Deputy Steel/Welding 4/27/2020 Partial Approval DARRYL ARNOLD
Interior/Exterior Lathing 4/29/2020 Corrections Issued MARK FERRARI
Final 5/12/2020 OK for CofC DARRYL ARNOLD
METHANE-Final 5/12/2020 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 5/12/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 5/12/2020 Approved DARRYL ARNOLD