2840 N PARTRIDGE AVE 90039

Certificate Information: 2840 N PARTRIDGE AVE 90039

Application / Permit
19016-10000-22743
Plan Check / Job No.
B19LA15217
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (2) NEW STEEL ORDINARY MOMENT FRAMES & NEW SHEAR WALL.
Permit Issued
Issued on 8/21/2020
Issuing Office
Metro
Current Status
CofC Issued on 12/22/2020

Permit Application Status History

Submitted 7/24/2019 APPLICANT
Assigned to Plan Check Engineer 8/21/2019 THOMAS SHERMAN
Corrections Issued 9/3/2019 THOMAS SHERMAN
Quality Review Completed 9/5/2019 HANS SANTIAGO
Building Plans Picked Up 9/17/2019 APPLICANT
Applicant returned to address corrections 1/22/2020 THOMAS SHERMAN
Plan Check Approved 1/30/2020 THOMAS SHERMAN
Issued 8/21/2020 APPLICANT
OK for CofC 12/16/2020 MARK FERRARI
CofC Issued 12/22/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 8/4/2020 STEVEN HOFSTAD

Contact Information

Contractor Thomas Construction Company; Lic. No.: 409151-B P O BOX 3034      SOUTH PASADENA, CA 91030
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12540 DESTINO ST      CERRITOS, CA 90703

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2020 Approved RAFAEL ESPINOZA
Deputy Drilled-In Anchors 9/21/2020 Conditional Approval MARK FERRARI
Deputy Wood Construction 9/21/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 10/13/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 10/20/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 10/29/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 10/30/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 11/4/2020 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 11/4/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 11/5/2020 Approved MARK FERRARI
Wood Frame 11/5/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 11/10/2020 Conditional Approval MARK FERRARI
Wood Frame 11/17/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 11/20/2020 Approved MARK FERRARI
Interior/Exterior Lathing 11/25/2020 Conditional Approval JONATHAN QUACH
Deputy Wood Construction 12/2/2020 Conditional Approval MARK FERRARI
Final 12/16/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/16/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 12/16/2020 Approved MARK FERRARI