2840 N PARTRIDGE AVE 90039
Certificate Information: 2840 N PARTRIDGE AVE 90039
- Application / Permit
- 19016-10000-22743
- Plan Check / Job No.
- B19LA15217
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (2) NEW STEEL ORDINARY MOMENT FRAMES & NEW SHEAR WALL.
- Permit Issued
- Issued on 8/21/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/22/2020
Permit Application Status History
| Submitted | 7/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2019 | THOMAS SHERMAN |
| Corrections Issued | 9/3/2019 | THOMAS SHERMAN |
| Quality Review Completed | 9/5/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 1/22/2020 | THOMAS SHERMAN |
| Plan Check Approved | 1/30/2020 | THOMAS SHERMAN |
| Issued | 8/21/2020 | APPLICANT |
| OK for CofC | 12/16/2020 | MARK FERRARI |
| CofC Issued | 12/22/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/4/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Thomas Construction Company; Lic. No.: 409151-B | P O BOX 3034 SOUTH PASADENA, CA 91030 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2020 | Approved | RAFAEL ESPINOZA |
| Deputy Drilled-In Anchors | 9/21/2020 | Conditional Approval | MARK FERRARI |
| Deputy Wood Construction | 9/21/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 10/13/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 10/20/2020 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/29/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 10/30/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 11/4/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 11/4/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 11/5/2020 | Approved | MARK FERRARI |
| Wood Frame | 11/5/2020 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 11/10/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 11/17/2020 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 11/20/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 11/25/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Wood Construction | 12/2/2020 | Conditional Approval | MARK FERRARI |
| Final | 12/16/2020 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 12/16/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 12/16/2020 | Approved | MARK FERRARI |