3550 S MENTONE AVE 90034
Certificate Information: 3550 S MENTONE AVE 90034
- Application / Permit
- 19016-10000-22685
- Plan Check / Job No.
- B19LA15192
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH 93. 1-SCCS AND SHEAR WALL.
- Permit Issued
- Issued on 1/16/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 4/3/2020
Permit Application Status History
| Submitted | 7/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/7/2019 | THOMAS SHERMAN |
| Corrections Issued | 8/12/2019 | THOMAS SHERMAN |
| Quality Review Completed | 8/13/2019 | SAI KHUM |
| Building Plans Picked Up | 8/16/2019 | APPLICANT |
| Applicant returned to address corrections | 9/16/2019 | THOMAS SHERMAN |
| Plan Check Approved | 9/23/2019 | THOMAS SHERMAN |
| Issued | 1/16/2020 | LADBS |
| OK for CofC | 3/19/2020 | GRANT WOODS |
| CofC Issued | 4/3/2020 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/11/2019 | CHARLES GARCIA |
Contact Information
| Contractor | C A C Design Development Inc; Lic. No.: 1055198-B | 1616 MENLO AVENUE LOS ANGELES, CA 90006 |
| Engineer | Kim,, Eui S; Lic. No.: S5138 | 37325 8TH AVE S FEDERAL WAY, WA 98003 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/30/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 1/30/2020 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 1/30/2020 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 1/30/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 2/4/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 2/6/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 2/7/2020 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 2/12/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Structural Steel Frame | 2/12/2020 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Wood Construction | 2/13/2020 | Conditional Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2020 | Partial Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 2/14/2020 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 2/14/2020 | Approved | PAUL DAVIDSON |
| Deputy Wood Construction | 2/21/2020 | Approved | TED RIES |
| Wood Frame | 2/25/2020 | Partial Approval | PAUL DAVIDSON |
| Deputy Wood Construction | 2/26/2020 | Conditional Approval | GRANT WOODS |
| Wood Frame | 2/27/2020 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 3/5/2020 | Not Ready for Inspection | GRANT WOODS |
| Interior/Exterior Lathing | 3/6/2020 | Approved | PAUL DAVIDSON |
| Final | 3/19/2020 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/19/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 3/19/2020 | Approved | GRANT WOODS |