8830 N ETIWANDA AVE 91325
Certificate Information: 8830 N ETIWANDA AVE 91325
- Application / Permit
- 19016-10000-22473
- Plan Check / Job No.
- B19LA15039
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 2 MF FOR LATERAL AND 1 COLUMN.
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/1/2021
Permit Application Status History
| Submitted | 7/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2019 | DANIEL YIP |
| Corrections Issued | 8/27/2019 | DANIEL YIP |
| Quality Review Completed | 8/29/2019 | SAI KHUM |
| Building Plans Picked Up | 9/5/2019 | APPLICANT |
| Applicant returned to address corrections | 10/17/2019 | DANIEL YIP |
| Plan Check Approved | 12/9/2019 | DANIEL YIP |
| Issued | 2/21/2020 | LADBS |
| OK for CofC | 6/29/2021 | JONATHAN QUACH |
| CofC Issued | 7/1/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/28/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Rigid Design & Construction Inc; Lic. No.: 947498-B | 14813 MORRISON ST SHERMAN OAKS, CA 91403 |
| Engineer | Bayat,, Hooman; Lic. No.: C79761 | 14813 MORRISON ST SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/4/2020 | Corrections Issued | JONATHAN QUACH |
| Deputy Reinf. Concrete | 3/26/2020 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Masonry | 3/26/2020 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/27/2020 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 4/15/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 4/15/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Steel/Welding | 4/21/2020 | Conditional Approval | JONATHAN QUACH |
| Structural Steel Frame | 4/23/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 4/23/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 5/14/2020 | Approved | DANIEL VARNUM |
| Smoke Detectors | 5/14/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 6/3/2020 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 6/3/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 6/3/2020 | Approved | DANIEL VARNUM |
| Special/Order Compliance | 4/15/2021 | Partial Inspection | DANIEL VARNUM |
| Final | 6/29/2021 | OK for CofC | JONATHAN QUACH |