13955 W OXNARD ST 91401

Certificate Information: 13955 W OXNARD ST 91401

Application / Permit
19016-10000-22388
Plan Check / Job No.
B19LA14996
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL PLYWOOD SHEARWALL. JUSTIFY EXISTING CONCRETE SHEAR WALL IS ADEQUATE. REINFORCE CONCRETE SHEAR WALL DRAG/COLLECTOR
Permit Issued
Issued on 6/10/2021
Issuing Office
Current Status
CofC Issued on 3/18/2022

Permit Application Status History

Submitted 7/23/2019 APPLICANT
Assigned to Plan Check Engineer 8/14/2019 MANUEL MONTUFAR
Corrections Issued 8/26/2019 MANUEL MONTUFAR
Quality Review Completed 8/29/2019 HANS SANTIAGO
Applicant returned to address corrections 10/11/2019 MANUEL MONTUFAR
Applicant returned to address corrections 1/10/2020 MANUEL MONTUFAR
Plan Check Approved 1/31/2020 MANUEL MONTUFAR
Issued 6/10/2021 APPLICANT
OK for CofC 3/11/2022 KENNETH ROBERTS
CofC Issued 3/18/2022 HENRY BAGHDASSARIAN

Permit Application Clearance Information

Metro Rail approval Cleared 10/7/2019 MANUEL MONTUFAR
Housing rent stabilization Cleared 6/9/2021 PHILLIP MUNGUIA

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Funk,, David Lyle; Lic. No.: NA5421       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/15/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 6/25/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 6/25/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 6/25/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 6/25/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 6/25/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Wood Construction 6/29/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 6/29/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 6/29/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 6/29/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 6/29/2021 Corrections Issued JOE VELASQUEZ
Insulation 7/1/2021 Partial Approval JOE VELASQUEZ
Reinforced Concrete Frame 7/9/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/9/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/9/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Wood Construction 7/12/2021 No Access for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 7/13/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/13/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/13/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 7/16/2021 Approved JOE VELASQUEZ
Final 7/23/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 7/23/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 7/23/2021 Not Ready for Inspection JOE VELASQUEZ
Final 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 7/29/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Steel/Welding 1/5/2022 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 2/22/2022 Approved KENNETH ROBERTS
Wood Frame 2/22/2022 Approved KENNETH ROBERTS
Interior/Exterior Lathing 2/28/2022 Approved KENNETH ROBERTS
Final 3/11/2022 OK for CofC KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 3/11/2022 Approved KENNETH ROBERTS