12609 W INDIANAPOLIS ST 90066

Certificate Information: 12609 W INDIANAPOLIS ST 90066

Application / Permit
19016-10000-22124
Plan Check / Job No.
B19LA14874
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE TO BE CONVERTED TO ACCESSORY DWELLING UNIT PER AB494 AND SB229.
Permit Issued
Issued on 10/1/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2019 APPLICANT
Assigned to Plan Check Engineer 7/26/2019 GEORGE ALVAREZ
Corrections Issued 7/26/2019 GEORGE ALVAREZ
Applicant returned to address corrections 9/23/2019 ADAM HEGAZI
Plan Check Approved 9/23/2019 CRISTINA SALAZAR
Issued 10/1/2020 APPLICANT
CofO in Progress 5/20/2022 JESUS RODRIGUEZ
Permit Finaled 5/26/2022 DANIEL ORRANTE
CofO Issued 5/26/2022 DANIEL ORRANTE
Permit Finaled 5/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/30/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 7/30/2019 ELAINE LEI
Sewer availability Cleared 7/30/2019 ELAINE LEI
Specific Plan Cleared 7/30/2019 JOE LUCKEY
Construction near power lines Cleared 9/18/2019 RIDWAN HARDY
Construction within easement Cleared 9/18/2019 RIDWAN HARDY
Grading Pre-Inspection Cleared 9/20/2019 PATRICK MISCHLICH

Contact Information

Contractor Guardado Pedro; Lic. No.: 1029838-B 1347 W GAGE AVE      LOS ANGELES, CA 90044
Engineer Perez,, Manuel Armando; Lic. No.: C73786 20850 SORRENTO LN      PORTER RANCH, CA 91326

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/24/2020 Partial Approval JOHNNY MIRANDA
Underground Mechanical 11/24/2020 Partial Approval JOHNNY MIRANDA
Sewer 11/30/2020 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 12/16/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 12/18/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/15/2021 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 2/4/2021 Not Ready for Inspection PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Partial Approval PIERRE VEGA
BUILDING-Rough-Frame 2/23/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 2/23/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 2/23/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/2/2021 Approved ENRIQUE MIRELES
Insulation 3/19/2021 Approved ENRIQUE MIRELES
Drywall Nailing 4/1/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/6/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/5/2021 Partial Approval STEPHANIE SWANSON
Shower Pan 11/17/2021 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 12/3/2021 Approved KRISTEN CAUSEY
ELECTRICAL-Final 4/25/2022 Corrections Issued PATRICK QUALEY
Final 4/25/2022 Corrections Issued PATRICK QUALEY
HVAC-Final 4/25/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Final 4/25/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 4/25/2022 SGSOV Approved PATRICK QUALEY
Smoke Detectors 4/25/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Final 5/11/2022 Approved JESUS RODRIGUEZ
Final 5/11/2022 Conditional Approval JESUS RODRIGUEZ
Gas Test 5/11/2022 Approved JESUS RODRIGUEZ
HVAC-Final 5/11/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 5/11/2022 Approved JESUS RODRIGUEZ
Smoke Detectors 5/11/2022 Approved JESUS RODRIGUEZ