1322 S 2ND AVE 90019

Certificate Information: 1322 S 2ND AVE 90019

Application / Permit
19016-10000-22110
Plan Check / Job No.
B19LA14865
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL (2) NEW STEEL CANTILEVER COLUMNS.
Permit Issued
Issued on 6/23/2022
Issuing Office
Current Status
CofC Issued on 6/26/2024

Permit Application Status History

Submitted 7/22/2019 APPLICANT
Assigned to Plan Check Engineer 8/14/2019 DANIEL SANJUAN
Corrections Issued 8/21/2019 DANIEL SANJUAN
Quality Review Completed 8/28/2019 HANS SANTIAGO
Plan Check Approved 1/9/2020 DANIEL SANJUAN
Issued 6/23/2022 APPLICANT
OK for CofC 6/26/2024 DARRYL ARNOLD
CofC Issued 6/26/2024 WINSTON DUNNING

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 12/12/2019 SOPHIE GABEL-SCHEINBAU
Housing rent stabilization Cleared 6/7/2022 MICHAEL SOTO

Contact Information

Contractor Cedar Construction & Development Inc; Lic. No.: 554550-B 10234 NATIONAL BLVD #1      LOS ANGELES, CA 90034
Engineer Alexander,, Andy Joseph; Lic. No.: C84086 1730 E HOLLY AVE STE 107      EL SEGUNDO, CA 90245

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/11/2022 Conditional Approval BRUCE CAMPBELL
Deputy Drilled-In Anchors 7/14/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 7/14/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/18/2022 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 7/19/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 7/29/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 7/29/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 8/1/2022 Approved BRUCE CAMPBELL
Deputy Reinf. Concrete 8/2/2022 Conditional Approval DARRYL ARNOLD
Wall Anchors 9/6/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 10/25/2022 Conditional Approval DARRYL ARNOLD
Final 11/1/2022 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 11/1/2022 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 11/1/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 11/1/2022 Not Ready for Inspection DARRYL ARNOLD
Interior/Exterior Lathing 11/4/2022 Conditional Approval DARRYL ARNOLD
Final 12/16/2022 Corrections Issued DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/16/2022 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 12/16/2022 Approved DARRYL ARNOLD
Final 7/27/2023 Corrections Issued DARRYL ARNOLD
Final 6/26/2024 OK for CofC DARRYL ARNOLD