555 W 5TH ST 5TH FLR 90013
Certificate Information: 555 W 5TH ST 5TH FLR 90013
- Application / Permit
- 19016-10000-21938
- Plan Check / Job No.
- B19LA14746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- NON STRUCTURAL INTERIOR OFFICE TI. WORK INCLUDING NON BEARING PARTITIONS , NEW ELEVATOR DOOR LOBBY, CEILING, FINISHES, MILLWORK AND (E) RESTROOMS UPGRADED. NO CHANGE OF USE.
- Permit Issued
- Issued on 10/2/2020
- Issuing Office
- Current Status
- Permit Finaled on 3/31/2021
Permit Application Status History
| Submitted | 7/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/23/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/24/2020 | SHANGQIN XIE |
| Plan Check Approved | 9/4/2020 | MICHAEL LOPEZ |
| Issued | 10/2/2020 | APPLICANT |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
| Permit Finaled | 3/30/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| Fire Marshall Fire Life Safety | Cleared | 9/2/2020 | ANDREW KO |
Contact Information
| Architect | Calderon,, Fernando Alvaro; Lic. No.: C24574 | 39 LAS CASTANETAS RANCHO SANTA MARGARITA, CA 92688 |
| Contractor | J T M Construction Group Inc; Lic. No.: 956584-B | 44 WEST 28TH STREET 11TH FLOOR NEW YORK, NY 10001 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 11/16/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 11/16/2020 | Partial Approval | KATY RAMIREZ |
| Insulation | 11/18/2020 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 11/18/2020 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 12/22/2020 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 1/7/2021 | Partial Approval | DANIEL COLLINS |
| T-Bar Ceiling | 1/22/2021 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 2/5/2021 | Approved | KATY RAMIREZ |
| Final | 3/5/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 3/5/2021 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 3/5/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 3/19/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Green Building Final | 3/19/2021 | Approved | DANIEL COLLINS |
| Smoke Detectors | 3/19/2021 | Approved | DANIEL COLLINS |
| Final | 3/30/2021 | Permit Finaled | DANIEL COLLINS |
| Green Building Final | 3/30/2021 | Approved | DANIEL COLLINS |
| Smoke Detectors | 3/30/2021 | Approved | DANIEL COLLINS |