5215 N HARMONY AVE 91601

Certificate Information: 5215 N HARMONY AVE 91601

Application / Permit
19016-10000-21863
Plan Check / Job No.
B19LA14702
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL PLYWOOD SHEARWALLS.
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofC Issued on 12/17/2020

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 8/7/2019 VARAND SARKISIAN
Corrections Issued 8/16/2019 VARAND SARKISIAN
Quality Review Completed 8/26/2019 HANS SANTIAGO
Plan Check Approved 10/28/2019 VARAND SARKISIAN
Issued 7/28/2020 APPLICANT
OK for CofC 12/17/2020 MARK FERRARI
CofC Issued 12/17/2020 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 10/3/2019 ANNA VAN
Project located in CRA area Cleared 10/3/2019 JIM URQUHART
Housing rent stabilization Cleared 6/30/2020 STEVEN HOFSTAD

Contact Information

Contractor Rigid Design & Construction Inc; Lic. No.: 947498-B 14813 MORRISON ST      SHERMAN OAKS, CA 91403
Engineer Alexander,, Andy Joseph; Lic. No.: C84086 1730 E HOLLY AVE STE 107      EL SEGUNDO, CA 90245

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2020 Not Ready for Inspection JOE VELASQUEZ
Pre-Inspection 8/5/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 8/6/2020 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 8/7/2020 Approved JOE VELASQUEZ
Deputy Reinf. Concrete 8/11/2020 No Access for Inspection JOE VELASQUEZ
Wood Frame 8/19/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/20/2020 Partial Approval JOE VELASQUEZ
Insulation 8/26/2020 Approved JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/31/2020 Not Ready for Inspection JOE VELASQUEZ
Deputy Wood Construction 9/1/2020 No Access for Inspection JOE VELASQUEZ
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 9/3/2020 Approved JOE VELASQUEZ
Interior/Exterior Lathing 9/11/2020 Approved JOE VELASQUEZ
Final 10/8/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 10/8/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 10/8/2020 Not Ready for Inspection JOE VELASQUEZ
Final 12/17/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 12/17/2020 Approved MARK FERRARI