325 W 8TH ST 90731
Certificate Information: 325 W 8TH ST 90731
- Application / Permit
- 19016-10000-21817
- Plan Check / Job No.
- B19LA14672
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 2 CAR GARAGE INTO AN ADU PER AB 494 AND SB 229 PER WFPP
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/20/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2019 | ADAM HEGAZI |
| Corrections Issued | 7/17/2019 | ADAM HEGAZI |
| Plan Check Approved | 8/9/2019 | KEVIN MORALES |
| No Progress | 8/15/2019 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 1/21/2020 | SHANGQIN XIE |
| Issued | 1/21/2020 | LADBS |
| CofO in Progress | 5/13/2020 | ANSON MAGLASANG |
| Permit Finaled | 5/20/2020 | BOB DUNN |
| CofO Issued | 5/20/2020 | BOB DUNN |
| Permit Finaled | 5/20/2020 | BOB DUNN |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 7/17/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 7/17/2019 | JEANETTE VONG |
| Project located in CRA area | Cleared | 7/19/2019 | JIM URQUHART |
| "D" conditions | Cleared | 7/24/2019 | ZURIEL ESPINOSA |
| Community Plan Implem. Overlay | Cleared | 8/23/2019 | HERMINIGILDO AGUSTIN |
| Construction near power lines | Cleared | 11/24/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Sewer | 2/4/2020 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 2/11/2020 | Partial Approval | ANSON MAGLASANG |
| PLUMBING-Rough | 2/11/2020 | Partial Approval | ANSON MAGLASANG |
| Sewer | 2/11/2020 | Partial Approval | ANSON MAGLASANG |
| Underground Mechanical | 2/11/2020 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 2/19/2020 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 2/19/2020 | Corrections Issued | ANSON MAGLASANG |
| Green Building Rough | 2/19/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Wood Frame | 2/19/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| Special/Order Compliance | 3/11/2020 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 3/16/2020 | Approved | ANSON MAGLASANG |
| Green Building Rough | 3/16/2020 | Approved | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 3/16/2020 | Approved | ANSON MAGLASANG |
| Insulation | 3/17/2020 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 3/31/2020 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Final | 4/22/2020 | Corrections Issued | JOHN KLARIN |
| Final | 4/22/2020 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 4/22/2020 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 4/22/2020 | Approved | JOHN KLARIN |
| Smoke Detectors | 4/22/2020 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 5/4/2020 | Approved | JOHN KLARIN |
| Final | 5/4/2020 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Final | 5/4/2020 | Approved | JOHN KLARIN |
| PLUMBING-Final | 5/4/2020 | Approved | JOHN KLARIN |
| Smoke Detectors | 5/4/2020 | Approved | JOHN KLARIN |
| Final | 5/12/2020 | OK to Issue CofO | JOHN KLARIN |