325 W 8TH ST 90731

Certificate Information: 325 W 8TH ST 90731

Application / Permit
19016-10000-21817
Plan Check / Job No.
B19LA14672
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING 2 CAR GARAGE INTO AN ADU PER AB 494 AND SB 229 PER WFPP
Permit Issued
Issued on 1/21/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2019 APPLICANT
Assigned to Plan Check Engineer 7/17/2019 ADAM HEGAZI
Corrections Issued 7/17/2019 ADAM HEGAZI
Plan Check Approved 8/9/2019 KEVIN MORALES
No Progress 8/15/2019 CHRISTOPHER KOMANCHECK
Plan Check Approved 1/21/2020 SHANGQIN XIE
Issued 1/21/2020 LADBS
CofO in Progress 5/13/2020 ANSON MAGLASANG
Permit Finaled 5/20/2020 BOB DUNN
CofO Issued 5/20/2020 BOB DUNN
Permit Finaled 5/20/2020 BOB DUNN

Permit Application Clearance Information

Address approval Cleared 7/17/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/17/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 7/17/2019 JEANETTE VONG
Sewer availability Cleared 7/17/2019 JEANETTE VONG
Project located in CRA area Cleared 7/19/2019 JIM URQUHART
"D" conditions Cleared 7/24/2019 ZURIEL ESPINOSA
Community Plan Implem. Overlay Cleared 8/23/2019 HERMINIGILDO AGUSTIN
Construction near power lines Cleared 11/24/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/23/2020 Not Ready for Inspection ANSON MAGLASANG
Sewer 2/4/2020 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 2/11/2020 Partial Approval ANSON MAGLASANG
PLUMBING-Rough 2/11/2020 Partial Approval ANSON MAGLASANG
Sewer 2/11/2020 Partial Approval ANSON MAGLASANG
Underground Mechanical 2/11/2020 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 2/19/2020 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Rough 2/19/2020 Corrections Issued ANSON MAGLASANG
Green Building Rough 2/19/2020 Not Ready for Inspection ANSON MAGLASANG
Wood Frame 2/19/2020 Not Ready for Inspection ANSON MAGLASANG
Special/Order Compliance 3/11/2020 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 3/16/2020 Approved ANSON MAGLASANG
Green Building Rough 3/16/2020 Approved ANSON MAGLASANG
Rough-Elec/Plmb/HVAC 3/16/2020 Approved ANSON MAGLASANG
Insulation 3/17/2020 Approved ANSON MAGLASANG
Drywall Nailing 3/31/2020 Approved BRIAN CHRISTIAN
ELECTRICAL-Final 4/22/2020 Corrections Issued JOHN KLARIN
Final 4/22/2020 Corrections Issued JOHN KLARIN
Green Building Final 4/22/2020 Corrections Issued JOHN KLARIN
PLUMBING-Final 4/22/2020 Approved JOHN KLARIN
Smoke Detectors 4/22/2020 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 5/4/2020 Approved JOHN KLARIN
Final 5/4/2020 Not Ready for Inspection JOHN KLARIN
Green Building Final 5/4/2020 Approved JOHN KLARIN
PLUMBING-Final 5/4/2020 Approved JOHN KLARIN
Smoke Detectors 5/4/2020 Approved JOHN KLARIN
Final 5/12/2020 OK to Issue CofO JOHN KLARIN