2011 S BEDFORD ST 90034
Certificate Information: 2011 S BEDFORD ST 90034
- Application / Permit
- 19016-10000-21736
- Plan Check / Job No.
- B19LA14626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL ONE (N) SCCS
- Permit Issued
- Issued on 5/7/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 9/10/2020
Permit Application Status History
| Submitted | 7/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2019 | DANIEL SANJUAN |
| Corrections Issued | 8/23/2019 | DANIEL SANJUAN |
| Quality Review Completed | 8/29/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 8/30/2019 | APPLICANT |
| Plan Check Approved | 10/3/2019 | DANIEL SANJUAN |
| Issued | 5/7/2020 | LADBS |
| OK for CofC | 9/1/2020 | GRANT WOODS |
| CofC Issued | 9/10/2020 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/22/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 5104 GARDEN GROVE AVE TARZANA, CA 91356 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2020 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 6/15/2020 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 6/17/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 6/18/2020 | Approved | GRANT WOODS |
| Structural Steel Frame | 6/18/2020 | Approved | GRANT WOODS |
| Wood Frame | 6/18/2020 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 6/22/2020 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/22/2020 | Conditional Approval | PAUL DAVIDSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2020 | Approved | PAUL DAVIDSON |
| Wood Frame | 6/22/2020 | Approved | PAUL DAVIDSON |
| Interior/Exterior Lathing | 6/30/2020 | Approved | SORIN CIRSTOIU |
| Final | 9/1/2020 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/1/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 9/1/2020 | Approved | GRANT WOODS |