3707 S MAPLE AVE 90011
Certificate Information: 3707 S MAPLE AVE 90011
- Application / Permit
- 19016-10000-21129
- Plan Check / Job No.
- B19LA14261
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL 1 MOMENT FRAME AND SHEAR WALLS.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/11/2020
Permit Application Status History
| Submitted | 7/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2019 | THOMAS SHERMAN |
| Corrections Issued | 8/20/2019 | THOMAS SHERMAN |
| Quality Review Completed | 8/22/2019 | SAI KHUM |
| Building Plans Picked Up | 8/26/2019 | APPLICANT |
| Plan Check Approved | 10/15/2019 | THOMAS SHERMAN |
| Issued | 2/20/2020 | LADBS |
| OK for CofC | 6/10/2020 | JOEY BUCHANAN |
| CofC Issued | 6/11/2020 | NICK LAROCCA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2019 | GABRIEL ROBLES |
| Miscellaneous | Cleared | 9/16/2019 | GABRIEL ROBLES |
| Housing rent stabilization | Cleared | 1/22/2020 | STEVEN HOFSTAD |
Contact Information
| Architect | Kostic,, Vasa; Lic. No.: C10740 | 1827-10TH ST_#4 SANTA MONICA, CA 90404 |
| Contractor | Dhe Best Construction Inc; Lic. No.: 1051288-B | 5900 CANOGA AVE SUITE 308 WOODLAND HILLS, CA 91367 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2020 | Approved | DARRYL ARNOLD |
| Wall Anchors | 3/27/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 3/27/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 3/31/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 4/14/2020 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 4/16/2020 | Approved | JOEY BUCHANAN |
| Reinforced Concrete Frame | 4/16/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 4/16/2020 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 4/20/2020 | Conditional Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Approved | JOEY BUCHANAN |
| Insulation | 4/21/2020 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 4/29/2020 | Corrections Issued | MARK FERRARI |
| Final | 6/5/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 6/5/2020 | SGSOV Not Ready | JOEY BUCHANAN |
| Smoke Detectors | 6/5/2020 | Approved | JOEY BUCHANAN |
| Final | 6/10/2020 | OK for CofC | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2020 | SGSOV Approved | JOEY BUCHANAN |