- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install 3 new SCCS.
- Permit Issued
- Issued on 7/29/2021
- Issuing Office
- Current Status
- CofC Issued on 7/18/2022
Permit Application Status History
| Submitted | 7/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2019 | DANIEL YIP |
| Corrections Issued | 8/29/2019 | DANIEL YIP |
| Quality Review Completed | 9/5/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 10/21/2019 | DANIEL YIP |
| Plan Check Approved | 11/5/2019 | DANIEL YIP |
| Issued | 7/29/2021 | APPLICANT |
| OK for CofC | 7/11/2022 | DARRYL ARNOLD |
| CofC Issued | 7/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/24/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | H Z S Construction; Lic. No.: 1039476-B | 1720 E GARRY AVE #229 SANTA ANA, CA 92705 |
| Engineer | Shekaramiz,, Hamid; Lic. No.: C82784 | 2 TIMBRE RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/27/2021 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Conditional Approval | DARRYL ARNOLD |
| Pre-Inspection | 9/29/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 9/29/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 10/4/2021 | Order to Comply Issued | DARRYL ARNOLD |
| Deputy Wood Construction | 10/5/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/6/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/29/2021 | Not Ready for Inspection | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 11/1/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 11/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 12/9/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/9/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Final | 7/11/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | DARRYL ARNOLD |