5112 E RAPHAEL ST 90042
Certificate Information: 5112 E RAPHAEL ST 90042
- Application / Permit
- 19016-10000-20459
- Plan Check / Job No.
- B19LA13855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING RECREATION ROOM/ STROAGE INTO AN ACCESSORY DWELLING UNIT PER SB 229 & AB 494 WITH NEW ADDITION. ALL WORK PER TYPE V SHEET. "COMPLY WITH DEPARTMENT ORDER effective date 06/05/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 855998.
- Permit Issued
- Issued on 10/16/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/5/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/9/2019 | VU NGUYEN |
| Applicant returned to address corrections | 10/7/2019 | MICHAEL LOPEZ |
| Plan Check Approved | 10/10/2019 | KEVIN MORALES |
| Issued | 10/16/2019 | LADBS |
| CofO in Progress | 8/11/2020 | PATRICK LIEBREGT |
| CofO Issued | 9/15/2020 | DANIEL SANCHEZ |
| Permit Finaled | 9/15/2020 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 7/9/2019 | ELAINE LEI |
| Grading Pre-Inspection | Cleared | 7/10/2019 | PATRICK MISCHLICH |
| Construction near power lines | Cleared | 10/5/2019 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 10/7/2019 | EMIL KYUPELYAN |
Contact Information
| Contractor | 3.1 Construction; Lic. No.: 1018269-B | 14017 DUNROBIN AVE BELLFLOWER, CA 90706 |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/21/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/23/2019 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/16/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/21/2020 | Corrections Issued | JAVIER RAMOS |
| Underground Mechanical | 1/28/2020 | Partial Approval | JAVIER RAMOS |
| Excavation/Setback/Form/Re-Bar | 2/3/2020 | Approved | JAVIER RAMOS |
| ELECTRICAL-Rough | 3/18/2020 | Partial Approval | JAVIER RAMOS |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Not Ready for Inspection | JAVIER RAMOS |
| PLUMBING-Rough | 3/18/2020 | Partial Approval | JAVIER RAMOS |
| Wood Frame | 3/18/2020 | Not Ready for Inspection | JAVIER RAMOS |
| Insulation | 4/23/2020 | Approved | PATRICK LIEBREGT |
| Interior/Exterior Lathing | 4/23/2020 | Approved | PATRICK LIEBREGT |
| Drywall Nailing | 5/1/2020 | Approved | PATRICK LIEBREGT |
| Final | 6/17/2020 | Not Ready for Inspection | PATRICK LIEBREGT |
| SGSOV-Seismic Gas S/O Valve | 6/17/2020 | SGSOV Not Ready | PATRICK LIEBREGT |
| Smoke Detectors | 6/17/2020 | Approved | PATRICK LIEBREGT |
| BUILDING-Rough-Frame | 8/10/2020 | Approved | PATRICK LIEBREGT |
| Final | 8/10/2020 | OK to Issue CofO | PATRICK LIEBREGT |
| SGSOV-Seismic Gas S/O Valve | 8/10/2020 | SGSOV Approved | PATRICK LIEBREGT |