1555 N VINE ST 90028
Certificate Information: 1555 N VINE ST 90028
- Application / Permit
- 19016-10000-20108
- Plan Check / Job No.
- B19LA13648
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE PORTION OF 1ST FLOOR RETAIL TO LEASING OFFICE AND ADD NEW RAMP
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | PRANITA SHAH |
| Corrections Issued | 7/11/2019 | PRANITA SHAH |
| Applicant returned to address corrections | 10/3/2019 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/31/2019 | SINA KHOSRAVI |
| Plan Check Approved | 11/1/2019 | SINA KHOSRAVI |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 6/8/2021 | RUSSELL BONVOULOIR |
| CofO Issued | 6/8/2021 | ERNESTO CORRAL |
| Permit Finaled | 6/8/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 9/10/2019 | SOPHIE GABEL-SCHEINBAU |
| Historical monument | Cleared | 9/10/2019 | JIM URQUHART |
| Project located in CRA area | Cleared | 9/10/2019 | JIM URQUHART |
| ZA Case | Cleared | 9/10/2019 | SOPHIE GABEL-SCHEINBAU |
| City Hist. Cultural Monument | Cleared | 9/11/2019 | MELISSA JONES |
| Historic monument | Cleared | 9/11/2019 | MELISSA JONES |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/31/2019 | ERIK BEASLEY |
Contact Information
| Architect | Olsen,, Eric H; Lic. No.: C27721 | 3802 OSTROM AVE LONG BEACH, CA 90808 |
| Contractor | Five Star Ontario Inc; Lic. No.: 833492-B | 975 FEE DRIVE SACRAMENTO, CA 95815 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/2/2020 | Partial Inspection | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 7/17/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 7/31/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 8/6/2020 | Corrections Issued | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 8/7/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Reinf. Concrete | 8/18/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 9/28/2020 | Approved | RUSSELL BONVOULOIR |
| T-Bar Ceiling | 10/2/2020 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 10/5/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 10/9/2020 | Approved | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 10/22/2020 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 12/18/2020 | Conditional Approval | RUSSELL BONVOULOIR |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Approved | RUSSELL BONVOULOIR |
| Smoke Detectors | 12/18/2020 | Approved | RUSSELL BONVOULOIR |
| Final | 12/22/2020 | Conditional Approval | RUSSELL BONVOULOIR |