241 S WESTLAKE AVE 90057
Certificate Information: 241 S WESTLAKE AVE 90057
- Application / Permit
- 19016-10000-19829
- Plan Check / Job No.
- B19LA13427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. (1) SCCS
- Permit Issued
- Issued on 12/3/2020
- Issuing Office
- Current Status
- CofC Issued on 3/8/2021
Permit Application Status History
| Submitted | 6/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2019 | VARAND SARKISIAN |
| Corrections Issued | 8/6/2019 | VARAND SARKISIAN |
| Quality Review Completed | 8/6/2019 | SAI KHUM |
| Building Plans Picked Up | 8/9/2019 | APPLICANT |
| Applicant returned to address corrections | 8/29/2019 | VARAND SARKISIAN |
| Plan Check Approved | 11/21/2019 | VARAND SARKISIAN |
| Issued | 12/3/2020 | APPLICANT |
| OK for CofC | 3/5/2021 | MARK FERRARI |
| CofC Issued | 3/8/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 11/14/2019 | ROBERT DUFF |
| Abandoned oil well approval | Cleared | 11/14/2019 | ROBERT DUFF |
| Housing rent stabilization | Cleared | 11/16/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Ariel Muller; Lic. No.: 1026822-B | 525 N FULLER AVE LOS ANGELES, CA 90036 |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/4/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 12/17/2020 | Conditional Approval | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 12/18/2020 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 12/31/2020 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 1/4/2021 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 1/5/2021 | Approved | MARK FERRARI |
| Wood Frame | 1/5/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 1/7/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 1/11/2021 | Approved | MARK FERRARI |
| Final | 3/1/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 3/1/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 3/1/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 3/1/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 3/5/2021 | OK for CofC | MARK FERRARI |
| Smoke Detectors | 3/5/2021 | Approved | MARK FERRARI |