- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 2 (N) Steal Special Cantilever Columns and shear wall
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- Metro
- Current Status
- Issued on 8/6/2024
Permit Application Status History
| Submitted | 6/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2019 | ERICK RIVERA |
| Corrections Issued | 8/1/2019 | ERICK RIVERA |
| Quality Review Completed | 8/2/2019 | SAI KHUM |
| Building Plans Picked Up | 9/17/2019 | APPLICANT |
| Applicant returned to address corrections | 11/25/2019 | ERICK RIVERA |
| Applicant returned to address corrections | 1/29/2020 | THOMAS SHERMAN |
| Applicant returned to address corrections | 1/31/2020 | THOMAS SHERMAN |
| Plan Check Approved | 2/5/2020 | THOMAS SHERMAN |
| Issued | 8/6/2024 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 2/5/2020 | MAX LODER |
| Housing rent stabilization | Cleared | 6/18/2024 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Fox Construction; Lic. No.: 1014686-B | 15402 VOSE ST VAN NUYS, CA 91406 |
| Engineer | Quiaot,, Florentino V; Lic. No.: C38659 | 412 W 231ST ST CARSON, CA 90745 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/7/2024 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 8/7/2024 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 8/8/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/28/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 8/28/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 9/5/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 9/18/2024 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 9/18/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/19/2024 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 9/19/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/24/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 9/24/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/8/2024 | Corrections Issued | DARRYL ARNOLD |
| Final | 10/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 10/18/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/18/2024 | Corrections Issued | DARRYL ARNOLD |