5732 W LEXINGTON AVE 90038
Certificate Information: 5732 W LEXINGTON AVE 90038
- Application / Permit
- 19016-10000-19123
- Plan Check / Job No.
- B19LA13029
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL (N) SCCS AND DOUBLE SIDED PLYWOOD SHEAR WALL
- Permit Issued
- Issued on 6/16/2020
- Issuing Office
- Current Status
- CofC Issued on 3/23/2021
Permit Application Status History
| Submitted | 6/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2019 | DANIEL YIP |
| Corrections Issued | 7/30/2019 | DANIEL YIP |
| Quality Review Completed | 8/1/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 8/8/2019 | APPLICANT |
| Applicant returned to address corrections | 10/28/2019 | DANIEL YIP |
| Plan Check Approved | 10/31/2019 | DANIEL YIP |
| Issued | 6/16/2020 | APPLICANT |
| OK for CofC | 3/22/2021 | MARK FERRARI |
| CofC Issued | 3/23/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 10/31/2019 | JIM URQUHART |
| Housing rent stabilization | Cleared | 4/22/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Konstruct Inc; Lic. No.: 1037235-B | 3964 BIXBY DR LA VERNE, CA 91750 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/1/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| Pre-Inspection | 7/2/2020 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/23/2020 | Partial Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/7/2020 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 9/1/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| Footing/Foundation/Slab | 9/3/2020 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 9/8/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 9/15/2020 | Partial Inspection | MARK FERRARI |
| Deputy Wood Construction | 9/18/2020 | Conditional Approval | MARK FERRARI |
| Final | 10/22/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2020 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Not Ready | JONATHAN QUACH |
| Final | 2/11/2021 | Conditional Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 2/11/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 2/11/2021 | Approved | JONATHAN QUACH |
| Final | 3/22/2021 | OK for CofC | MARK FERRARI |