5887 N WHITNALL HWY 91601
Certificate Information: 5887 N WHITNALL HWY 91601
- Application / Permit
- 19016-10000-18806
- Plan Check / Job No.
- B19LA12832
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93. INSTALL 2 (N) SCCS,
- Permit Issued
- Issued on 12/16/2020
- Issuing Office
- Current Status
- CofC Issued on 12/22/2022
Permit Application Status History
| Submitted | 6/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2019 | VARAND SARKISIAN |
| Corrections Issued | 7/25/2019 | VARAND SARKISIAN |
| Re-Submittal Required | 7/26/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 8/29/2019 | APPLICANT |
| Re-Submitted | 3/19/2020 | VARAND SARKISIAN |
| Corrections Issued 2 | 3/19/2020 | VARAND SARKISIAN |
| Submitted for Second Quality Review | 3/19/2020 | VARAND SARKISIAN |
| Quality Review Completed | 3/19/2020 | HANS SANTIAGO |
| Plan Check Approved | 3/19/2020 | VARAND SARKISIAN |
| Issued | 12/16/2020 | APPLICANT |
| OK for CofC | 11/4/2022 | KENNETH ROBERTS |
| CofC Issued | 12/22/2022 | RICKEY JACKSON |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/9/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/24/2022 | Partial Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 8/31/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 9/7/2022 | Approved | KENNETH ROBERTS |
| Structural Steel Frame | 9/7/2022 | Approved | KENNETH ROBERTS |
| Deputy Wood Construction | 9/9/2022 | Conditional Approval | KENNETH ROBERTS |
| Wood Frame | 9/16/2022 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 10/5/2022 | Approved | KENNETH ROBERTS |
| Final | 10/26/2022 | Partial Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/26/2022 | Approved | KENNETH ROBERTS |
| Final | 10/27/2022 | Corrections Issued | KENNETH ROBERTS |
| Final | 11/4/2022 | OK for CofC | KENNETH ROBERTS |