4936-4938 E STRATFORD ROAD 90042

Certificate Information: 4936-4938 E STRATFORD ROAD 90042

Application / Permit
19016-10000-18398
Plan Check / Job No.
B19LA12568
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT A PORTION OF AN EXISTING GARAGE IN TO ACCESSORY DWELLING UNIT. PORTION OF GARAGE & UNIT ABOVE TO REMAIN.
Permit Issued
Issued on 9/2/2021
Issuing Office
Current Status
Issued on 9/2/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2019 APPLICANT
Assigned to Plan Check Engineer 7/24/2019 PRANITA SHAH
Corrections Issued 8/12/2019 PRANITA SHAH
Quality Review Completed 8/12/2019 TU HUA
Applicant returned to address corrections 5/15/2020 PRANITA SHAH
Green Plans Picked Up 8/19/2020 APPLICANT
Plan Check Approved 11/24/2020 PRANITA SHAH
Issued 9/2/2021 APPLICANT
Building Plans Picked Up 9/8/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/27/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/27/2019 JEANETTE VONG
Grading Pre-Inspection Cleared 9/27/2019 PATRICK MISCHLICH
Housing rent stabilization Cleared 9/27/2019 MICHAEL SOTO
Sewer availability Cleared 9/27/2019 JEANETTE VONG
Green Code Cleared 7/23/2020 VIVIAN LAO
Hydrant and Access approval Cleared 7/29/2020 KURT CORRAL
Address approval Cleared 11/12/2020 CECILIO NAVARRO
Sewer availability Cleared 7/26/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/4/2021 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 2/17/2022 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/25/2022 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 4/5/2023 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 6/26/2025 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/18/2025 Partial Approval SCOTT FINNILA
HVAC-Rough 7/18/2025 Corrections Issued SCOTT FINNILA
Rough-Elec/Plmb/HVAC 7/18/2025 Approved SCOTT FINNILA
BUILDING-Rough-Frame 8/13/2025 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 8/13/2025 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 8/13/2025 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 9/4/2025 Approved SCOTT FINNILA
Green Building Rough 9/4/2025 Approved SCOTT FINNILA
Insulation 9/4/2025 Approved SCOTT FINNILA
Drywall Nailing 10/10/2025 Approved SCOTT FINNILA
Shower Pan 2/25/2026 Approved SCOTT FINNILA
Special/Order Compliance 2/26/2026 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 3/16/2026 Approved SCOTT FINNILA