1732 S 6TH AVE 90019
Certificate Information: 1732 S 6TH AVE 90019
- Application / Permit
- 19016-10000-18119
- Plan Check / Job No.
- B19LA12422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY RETROFIT PER LABC CHAPTER 93. INSTALL (2) STEEL SPECIAL CANTILEVER COLUMNS
- Permit Issued
- Issued on 9/21/2020
- Issuing Office
- Current Status
- CofC Issued on 2/10/2021
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2019 | BIDYUT RATH |
| Corrections Issued | 7/16/2019 | BIDYUT RATH |
| Quality Review Completed | 7/16/2019 | SAI KHUM |
| Building Plans Picked Up | 7/22/2019 | APPLICANT |
| Applicant returned to address corrections | 3/12/2020 | BIDYUT RATH |
| Plan Check Approved | 3/23/2020 | BIDYUT RATH |
| No Progress | 6/10/2020 | DANIEL SANJUAN |
| Plan Check Approved | 8/25/2020 | DANIEL SANJUAN |
| Issued | 9/21/2020 | APPLICANT |
| OK for CofC | 2/10/2021 | JONATHAN QUACH |
| CofC Issued | 2/10/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 1/30/2020 | JASON CHAN |
| Housing rent stabilization | Cleared | 9/14/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 11/25/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 11/25/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/25/2020 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/3/2020 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/21/2020 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/21/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 1/19/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 1/19/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 1/19/2021 | Approved | DARRYL ARNOLD |
| Final | 1/29/2021 | Conditional Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Approved | JONATHAN QUACH |
| Final | 2/10/2021 | OK for CofC | JONATHAN QUACH |