1580 E INDUSTRIAL ST 90021
Certificate Information: 1580 E INDUSTRIAL ST 90021
- Application / Permit
- 19016-10000-18092
- Plan Check / Job No.
- B19LA12396
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- FOR CHANGE OF USE FROM WAREHOUSE TO RESTAURANT WITH BACK OF HOUSE OFFICE SPACE. STRUCTRUAL UPGRADE & INTERIOR T.I. WORK.
- Permit Issued
- Issued on 1/4/2021
- Issuing Office
- Current Status
- CofO Issued on 4/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | JOE VO |
| Corrections Issued | 7/30/2019 | JOE VO |
| Quality Review Completed | 8/5/2019 | GARO TELMI |
| Building Plans Picked Up | 8/6/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 8/6/2019 | APPLICANT |
| Applicant returned to address corrections | 10/19/2020 | JOE VO |
| Applicant returned to address corrections | 10/26/2020 | JOE VO |
| Green Plans Picked Up | 11/12/2020 | APPLICANT |
| Plan Check Approved | 12/22/2020 | JOE VO |
| Issued | 1/4/2021 | APPLICANT |
| CofO in Progress | 4/7/2022 | RAFAEL ESPINOZA |
| CofO Issued | 4/7/2022 | TERRY HERR |
| Permit Finaled | 4/7/2022 | TERRY HERR |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/24/2019 | THOMAS LANG |
| ZI | Cleared | 5/22/2020 | DANIEL CORONADO |
| Fire Marshall Fire Life Safety | Cleared | 6/9/2020 | OSCAR SALGADO JR |
| Food Service Establishment | Cleared | 8/3/2020 | KENNETH BROWNE |
| CPC | Cleared | 8/26/2020 | CLAUDE GOODING |
| Comm Cor/Mini-Mall | Cleared | 8/26/2020 | CLAUDE GOODING |
| Hydrant and Access approval | Cleared | 8/31/2020 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 9/3/2020 | WESTON PRINGLE |
| Sewer availability | Cleared | 10/20/2020 | JEANIE LAM |
| Food establishment approval | Cleared | 10/23/2020 | LACDHS APPROVED |
| Green Code | Cleared | 10/26/2020 | VIVIAN LAO |
| Miscellaneous | Cleared | 10/26/2020 | JOE VO |
| DAS Clearance | Cleared | 12/3/2020 | JOE VO |
Contact Information
| Contractor | Spacecraft; Lic. No.: 821656-B | 7507 W SUNSET BLVD #12 LOS ANGELES, CA 90046 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/6/2021 | Not Ready for Inspection | LANNY MERRICK |
| T-Bar Ceiling | 1/6/2021 | Not Ready for Inspection | LANNY MERRICK |
| Verify Rec and Parks Fee Memo | 1/6/2021 | Not Ready for Inspection | LANNY MERRICK |
| Wood Frame | 1/6/2021 | Not Ready for Inspection | LANNY MERRICK |
| Deputy Drilled-In Anchors | 1/8/2021 | Conditional Approval | RONALD PACHECO |
| Drywall Nailing | 3/30/2021 | Corrections Issued | RONALD PACHECO |
| Drywall Nailing | 4/12/2021 | Not Ready for Inspection | RONALD PACHECO |
| T-Bar Ceiling | 4/12/2021 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 4/12/2021 | Not Ready for Inspection | RONALD PACHECO |
| Drywall Nailing | 4/14/2021 | Not Ready for Inspection | RONALD PACHECO |
| T-Bar Ceiling | 4/14/2021 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 4/14/2021 | Not Ready for Inspection | RONALD PACHECO |
| Drywall Nailing | 6/14/2021 | Approved | JONATHAN QUACH |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 6/14/2021 | Approved | JONATHAN QUACH |
| T-Bar Ceiling | 6/14/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 6/14/2021 | Approved | JONATHAN QUACH |
| Final | 11/12/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Final | 11/12/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Rough | 11/12/2021 | Approved | JONATHAN QUACH |
| Reinforced Concrete Frame | 11/12/2021 | Approved | JONATHAN QUACH |
| Reinforced Masonry Frame | 11/12/2021 | Approved | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 11/12/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 2/10/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Final | 2/10/2022 | Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 2/10/2022 | Approved | RAFAEL ESPINOZA |
| Final | 2/16/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 2/23/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Final | 3/2/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 3/3/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 3/8/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 3/10/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 3/30/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 4/4/2022 | Corrections Issued | RAFAEL ESPINOZA |
| Final | 4/7/2022 | Conditional Approval | RAFAEL ESPINOZA |