11601 W WASHINGTON PL 90066
Certificate Information: 11601 W WASHINGTON PL 90066
- Application / Permit
- 19016-10000-18063
- Plan Check / Job No.
- B19LA12380
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Child Care Facility
- Work Description
- Change of use from retail store to child care center and re-striping parking spaces.
- Permit Issued
- Issued on 9/28/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | HELEN NGUYEN |
| Corrections Issued | 7/9/2019 | HELEN NGUYEN |
| Disabled Access Plans Picked Up | 7/25/2019 | APPLICANT |
| Quality Review Completed | 8/3/2019 | YOUNG KIM |
| Applicant returned to address corrections | 3/9/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/19/2020 | HELEN NGUYEN |
| Plan Check Approved | 6/4/2020 | HELEN NGUYEN |
| Building Plans Picked Up | 6/5/2020 | APPLICANT |
| Issued | 9/28/2020 | APPLICANT |
| CofO in Progress | 6/24/2021 | SORIN CIRSTOIU |
| CofO in Progress | 6/28/2021 | SORIN CIRSTOIU |
| Permit Finaled | 6/29/2021 | TED RIES |
| CofO Issued | 6/29/2021 | TED RIES |
| Permit Finaled | 6/29/2021 | TED RIES |
Permit Application Clearance Information
| DAS Clearance | Cleared | 9/19/2019 | HELEN NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 9/27/2019 | JEANETTE VONG |
| Specific Plan | Cleared | 2/27/2020 | PEDRO AYALA |
| Fire Marshall Fire Life Safety | Cleared | 4/9/2020 | ANDREW KO |
Contact Information
| Contractor | Cook Matthew; Lic. No.: 1013539-B | 1163 CHEROKEE TOPANGA, CA 90290 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 10/21/2020 | Not Ready for Inspection | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 10/30/2020 | Conditional Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 11/2/2020 | Approved | SORIN CIRSTOIU |
| Wood Frame | 11/12/2020 | Not Ready for Inspection | SORIN CIRSTOIU |
| Wood Frame | 11/20/2020 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 12/9/2020 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 12/18/2020 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 12/23/2020 | Partial Approval | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 2/5/2021 | Conditional Approval | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 2/8/2021 | Approved | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 2/8/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 3/26/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Not Ready | LEOPOLDO MENDOZA |
| Smoke Detectors | 3/26/2021 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 3/26/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 6/18/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/18/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Final | 6/23/2021 | Partial Approval | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/23/2021 | SGSOV Approved | SORIN CIRSTOIU |
| Final | 6/28/2021 | OK to Issue CofO | SORIN CIRSTOIU |