110 E 9TH ST C150 90015
Certificate Information: 110 E 9TH ST C150 90015
- Application / Permit
- 19016-10000-18015
- Plan Check / Job No.
- B19LA12342
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- CHANGE OF USE FROM (E) OFFICE TO BANK ON GROUND FLOOR. NEW NON-STRUCTURAL WALLS, FURNITURE, FIXTURE AND FINISHES THROUGHOUT.
- Permit Issued
- Issued on 10/28/2019
- Issuing Office
- Metro
- Current Status
- Issued on 10/28/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2019 | KEVIN MORALES |
| Disabled Access Plans Picked Up | 7/24/2019 | APPLICANT |
| Corrections Issued | 8/1/2019 | KEVIN MORALES |
| Quality Review Completed | 8/18/2019 | YOUNG KIM |
| Building Plans Picked Up | 8/21/2019 | APPLICANT |
| Plan Check Approved | 9/16/2019 | KEVIN MORALES |
| Issued | 10/28/2019 | LADBS |
| TCO Issued (Expire Date: 08-04-2020) | 2/6/2020 | DAVID TSAU |
| TCO Issued (Expire Date: 01-27-2021) | 7/31/2020 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 07-19-2021) | 1/20/2021 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 02-13-2022) | 8/17/2021 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 09-11-2022) | 3/15/2022 | ERNESTO CORRAL |
| TCO Issued (Expire Date: 03-25-2023) | 9/26/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 9/10/2019 | ELIZABETH TOMS |
| "D" conditions | Cleared | 9/12/2019 | SARAHI ORTEGA |
| "Q" conditions | Cleared | 9/12/2019 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/12/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZA Case | Cleared | 9/12/2019 | SARAHI ORTEGA |
| ZI | Cleared | 9/13/2019 | CHI DANG |
Contact Information
| Architect | Stephenson,, Lonnie Robert; Lic. No.: C22710 | , |
| Contractor | Johnson & Jennings Incorporated; Lic. No.: 438867-B | 3870 MURPHY CANYON RD STE 110 SAN DIEGO, CA 92123 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 11/20/2019 | Corrections Issued | KATY RAMIREZ |
| Drywall Nailing | 1/9/2020 | Approved | KATY RAMIREZ |
| T-Bar Ceiling | 1/9/2020 | Not Ready for Inspection | KATY RAMIREZ |
| T-Bar Ceiling | 1/16/2020 | Partial Inspection | KATY RAMIREZ |
| Final | 1/23/2020 | Not Ready for Inspection | KATY RAMIREZ |
| METHANE-Final | 1/23/2020 | Approved | KATY RAMIREZ |
| METHANE-Rough | 1/23/2020 | Approved | KATY RAMIREZ |
| Reinforced Concrete Frame | 1/23/2020 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 1/23/2020 | SGSOV No Gas | KATY RAMIREZ |
| Smoke Detectors | 1/23/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 1/30/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Smoke Detectors | 1/30/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 2/5/2020 | Partial Inspection | KATY RAMIREZ |
| Smoke Detectors | 2/5/2020 | Approved | KATY RAMIREZ |
| Special/Order Compliance | 7/14/2020 | Approved | KATY RAMIREZ |
| Special/Order Compliance | 1/4/2021 | Conditional Approval | DANIEL COLLINS |
| Special/Order Compliance | 6/23/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Special/Order Compliance | 1/19/2022 | Approved | ERNESTO CORRAL |
| Special/Order Compliance | 8/17/2022 | Partial Approval | KATY RAMIREZ |
| Special/Order Compliance | 3/1/2023 | Partial Approval | KATY RAMIREZ |
| Final | 10/21/2024 | Corrections Issued | RONALD JIMENEZ |