3330 N CHAPMAN ST 90065

Certificate Information: 3330 N CHAPMAN ST 90065

Application / Permit
19016-10000-17267
Plan Check / Job No.
B19LA11846
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CH 93. INSTALL (6) SCCS.
Permit Issued
Issued on 7/13/2020
Issuing Office
Current Status
CofC Issued on 10/22/2020

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Assigned to Plan Check Engineer 7/2/2019 JESSE VIDUYA
Corrections Issued 7/10/2019 JESSE VIDUYA
Quality Review Completed 7/11/2019 SAI KHUM
Building Plans Picked Up 7/12/2019 APPLICANT
Applicant returned to address corrections 8/28/2019 JESSE VIDUYA
Plan Check Approved 9/23/2019 JESSE VIDUYA
Issued 7/13/2020 APPLICANT
OK for CofC 10/15/2020 MARK FERRARI
CofC Issued 10/22/2020 ERNESTO CORRAL

Permit Application Clearance Information

Supp. Use District POD/CDO/TDO Cleared 8/27/2019 RICHARD REASER
Housing rent stabilization Cleared 6/16/2020 MICHAEL GREGERSON

Contact Information

Contractor Brytin Construction; Lic. No.: 1065160-B 1140 AGNEW STREET      SIMI VALLEY, CA 93065
Engineer Farmand,, Anthony E; Lic. No.: C62595 2372 MORSE AVE STE 137      IRVINE, CA 92614

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2020 Approved MARK FERRARI
Wood Frame 7/28/2020 Partial Approval MARK FERRARI
Wood Frame 8/4/2020 Partial Approval MARK FERRARI
Deputy Drilled-In Anchors 8/5/2020 Conditional Approval MARK FERRARI
Deputy Reinf. Concrete 8/5/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 8/6/2020 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 8/21/2020 Approved MARK FERRARI
Wood Frame 8/21/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 8/24/2020 Conditional Approval MARK FERRARI
Wood Frame 8/26/2020 Partial Inspection MARK FERRARI
Structural Steel Frame 8/28/2020 Approved MARK FERRARI
Interior/Exterior Lathing 9/8/2020 Approved MARK FERRARI
Final 10/15/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 10/15/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 10/15/2020 Approved MARK FERRARI