1717 W VERNON AVE 90062
Certificate Information: 1717 W VERNON AVE 90062
- Application / Permit
- 19016-10000-17173
- Plan Check / Job No.
- B19LA11779
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL NEW MOMENT FRAME.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/18/2022
Permit Application Status History
| Submitted | 6/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/2/2019 | EVERARDO SANTOS |
| Corrections Issued | 7/12/2019 | EVERARDO SANTOS |
| Quality Review Completed | 7/12/2019 | SAI KHUM |
| Building Plans Picked Up | 8/6/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 8/6/2019 | APPLICANT |
| Applicant returned to address corrections | 10/3/2019 | EVERARDO SANTOS |
| Applicant returned to address corrections | 11/1/2019 | EVERARDO SANTOS |
| Plan Check Approved | 11/12/2019 | EVERARDO SANTOS |
| Issued | 2/18/2020 | LADBS |
| OK for CofC | 8/18/2022 | WINSTON DUNNING |
| CofC Issued | 8/18/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| DAS Clearance | Cleared | 10/9/2019 | ELIZABETH TOMS |
| Community Plan Implem. Overlay | Cleared | 11/5/2019 | ERIK BEASLEY |
| Community Plan Implem. Overlay | Cleared | 11/5/2019 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 11/5/2019 | ERIK BEASLEY |
| Work Adjacent to Public Way | Cleared | 11/6/2019 | ROSA SILVA |
| Housing rent stabilization | Cleared | 2/13/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Green Builders Associates Inc; Lic. No.: 938622-B | 1751 LA SENDA PL SO PASADENA, CA 91030 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/30/2020 | Corrections Issued | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 9/16/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/18/2020 | Approved | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 9/30/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 11/24/2020 | Approved | DARRYL ARNOLD |
| Wood Frame | 11/24/2020 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 12/9/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/10/2020 | Approved | JOEY BUCHANAN |
| Final | 2/4/2021 | Corrections Issued | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 2/4/2021 | Approved | DANIEL VARNUM |
| Final | 8/18/2022 | OK for CofC | WINSTON DUNNING |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | WINSTON DUNNING |