18362 W OXNARD ST 91356

Certificate Information: 18362 W OXNARD ST 91356

Application / Permit
19016-10000-16764
Plan Check / Job No.
B19LA11491
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
FOR CORE & SHELL-CHANGE OF USE FROM WAREHOUSE/OFFICE TO OFFICE. BUILDING #4.
Permit Issued
Issued on 2/18/2020
Issuing Office
Metro
Current Status
Permit Finaled on 6/16/2022

Permit Application Status History

Submitted 6/4/2019 APPLICANT
Green Plans Picked Up 6/12/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 TSE MING HUANG
Corrections Issued 6/25/2019 TSE MING HUANG
Quality Review Completed 7/13/2019 STANLEY RAAP
Building Plans Picked Up 7/17/2019 APPLICANT
Applicant returned to address corrections 11/19/2019 TSE MING HUANG
Applicant returned to address corrections 12/16/2019 TSE MING HUANG
Applicant returned to address corrections 1/15/2020 TSE MING HUANG
Plan Check Approved 2/3/2020 TSE MING HUANG
Issued 2/18/2020 LADBS
Refund in Progress 7/26/2021 TERENCE SHIA
Refund Denied 10/15/2021 EMILY HU
Issued 10/15/2021 EMILY HU
Permit Finaled 6/16/2022 CAMERON CHABAN

Permit Application Clearance Information

Address approval Cleared 9/9/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 9/9/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 9/9/2019 MARKOS PEREZ-BRAN
Green Code Cleared 11/12/2019 COLIN LOREDO
DAS Clearance Cleared 1/14/2020 TSE MING HUANG

Contact Information

Architect Wilder,, Arthur J; Lic. No.: C27915 3859 CARDIFF AVENUE      CULVER CITY, CA 90232
Contractor Parker Brown Inc; Lic. No.: 689613-B 6727 VARIEL AVENUE      CANOGA PARK, CA 913032811
Engineer Gavazza,, Jeffrey Bryan; Lic. No.: C59894 472 35TH ST      MANHATTAN BEACH, CA 90266
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/29/2020 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 6/3/2020 Order to Comply Issued ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Approved DANIEL VARNUM
Light Gage Steel Frame 7/29/2020 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 7/31/2020 Conditional Approval JEFFREY DURAN
Drywall Nailing 8/7/2020 Partial Approval DANIEL VARNUM
Deputy Steel/Welding 8/19/2020 Conditional Approval PAUL DAVIDSON
Deputy Steel/Welding 8/21/2020 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 8/24/2020 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 8/25/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 8/28/2020 Conditional Approval PAUL DAVIDSON
Final 2/16/2022 OK to Expire Permit CAMERON CHABAN
Green Building Final 2/16/2022 Approved CAMERON CHABAN
Green Building Rough 2/16/2022 Approved CAMERON CHABAN
Reinforced Masonry Frame 2/16/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 2/16/2022 Approved CAMERON CHABAN
Final 5/17/2022 Partial Inspection CAMERON CHABAN
Final 6/16/2022 Permit Finaled CAMERON CHABAN